01
Preserve exact state
Every assertion names the C-code, bounded scope, supporting claim and source IDs, verification date and reopen trigger.
Public production release · indexing enabled
Methodology
A later state is recorded only when function-appropriate evidence supports it. No wording, badge or figure carries a project beyond the exact state and scope established by the source record.
01
Every assertion names the C-code, bounded scope, supporting claim and source IDs, verification date and reopen trigger.
02
Requested, studied, approved, contracted, deliverable, energized, average, peak, MW-IT and forecast values remain separate.
03
The page says what the evidence establishes and what it does not establish, including relevant contrary evidence and negative findings.
04
A record changes after a specified public event or document is checked, not because time passed or an announcement sounded definitive.
Four-register discipline
Movement between registers requires an explicit, source-stated bridge. Missing bridge data remains unknown rather than being imputed.
R01
Requests, forecasts, design power, energized load, average MW and energy remain distinct.
CLM-0005CLM-0033
R02
Service model, deliverability, generation and physical inputs stay attached to their own pathway.
CLM-0053
R03
Capex, backlog, RPO, contracted power, revenue and utilization are not bridge-equivalent.
CLM-0180
R04
Total data-center measures are not AI-only unless the source supplies the cut.
CLM-0029
C7–C10 · service-model fork
Before a C7–C10 state is assigned, the record must identify the authority, instrument and service model that governs the load.
CLM-0053TERM-120
CLM-0053 · interpretation
No single U.S. “grid interconnection” state applies to all large loads: retail load service/interconnection, transmission service, generator interconnection, co-location, and behind-the-meter arrangements use different actors, instruments, studies, and jurisdictional pathways.
Unit integrity
CLM-0005 · interpretation
Announced, requested, approved, contracted, deliverable, energized, installed, utilized, and economically productive capacity are non-equivalent states and units.
SRC-0001internal recordSRC-0002internal recordCLM-0033 · interpretation
TWh/year, equivalent average GW, source-defined facility capacity, system peak GW, requested load, design capacity, MW-IT, GPU count, and announced capex are non-interchangeable metrics and are held in separate comparable groups.
C0–C21
Code order describes the ontology. It is not a completion percentage, probability or quality score.
Establishes: A dated record supports only a concept, rumor, or pre-announcement indication.
Does not prove: A public announcement, site, land right, permit, utility request, contract, construction, power delivery, operation, use, utilization, revenue, or economic capacity.
Establishes: A public party has announced a bounded project or plan.
Does not prove: A secured site, land control, zoning, utility request, approved service, agreement, funded upgrade, construction, energized power, operation, utilization, or economic capacity.
Establishes: A location has been publicly identified for the bounded scope.
Does not prove: A land option or control, zoning application/approval, service request, agreement, construction, energized power, operation, or economic capacity.
Establishes: A land option or active negotiation is evidenced for the bounded scope.
Does not prove: Land control, zoning approval, utility service, agreement, construction, energized power, operation, or economic capacity.
Establishes: The relevant land is controlled under the evidenced instrument and scope.
Does not prove: Zoning approval, utility service, agreement, construction, energized power, operation, or economic capacity.
Establishes: A zoning or land-use application has been filed.
Does not prove: Approval, survival of appeal, utility service, agreement, construction, energized power, operation, or economic capacity.
Establishes: A specified land-use approval has been granted.
Does not prove: Finality against appeal, utility service, deliverability, agreement, construction, energized power, operation, or economic capacity.
Establishes: A request entered the applicable utility/interconnection process for the stated scope.
Does not prove: Study acceptance, approval, deliverability, tariff pathway, executed agreement, construction, energized load, operation, or economic capacity.
Establishes: A specified study/review has been accepted or entered the evidenced stage.
Does not prove: A service pathway, executed agreement, funded upgrades, deliverable/firm power, construction, energization, operation, or economic capacity.
Establishes: An applicable tariff, service category, or regulatory pathway exists for the stated scope.
Does not prove: Customer participation, executed agreement, funded upgrades, deliverability, construction, energized power, operation, or economic capacity.
Establishes: A specified agreement or binding obligation is evidenced.
Does not prove: Physical delivery, firm/deliverable service beyond the instrument, funded or completed upgrades, construction, energization, commissioning, operation, use, utilization, or economic capacity.
Establishes: Funding or financial responsibility for specified upgrades is evidenced.
Does not prove: Completed upgrades, equipment delivery, energization, commissioning, IT installation, operation, use, utilization, or economic capacity.
Establishes: Physical construction has begun for the specified scope.
Does not prove: Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Establishes: Specified major equipment has been delivered for the bounded scope.
Does not prove: Installation, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Establishes: The specified electrical supply or facility scope has been energized.
Does not prove: Full commissioning, stated MW operating continuously, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Establishes: The specified facility/system has passed the evidenced commissioning or acceptance scope.
Does not prove: IT installation, cluster operation, customer use, utilization/revenue, sustained economics, or completion of unevidenced phases.
Establishes: The specified IT capacity has been installed.
Does not prove: Cluster operation, customer use, measured utilization, revenue effect, sustained economic capacity, or equivalence to site power.
Establishes: The specified compute cluster is operating under the evidenced source and scope.
Does not prove: Measured operating MW, customer use, utilization, revenue, profitability, sustained economic capacity, or operation of every phase.
Establishes: Customer workload or contracted use is observed for the specified scope.
Does not prove: Measured utilization/revenue at the required basis, profitability, sustained economic capacity, or permanence.
Establishes: Specified utilization or revenue evidence is observed for the defined period and boundary.
Does not prove: Sustained economic capacity outside the evidenced period/scope, profitability unless shown, permanence, or full-campus realization.
Establishes: Sustained economic operation is evidenced for the stated boundary, method, and period.
Does not prove: Permanence, all phases or sites, future growth, general market success, or transferability beyond the evidenced scope.
Establishes: An adverse or changed-status subtype is evidenced for the specified scope and date.
Does not prove: A universal terminal state, erasure of historical states, final cancellation when only delay/appeal is shown, or failure of related phases/projects.
Traceability model
Contrary evidence narrows the permitted claim. A negative finding records what the reviewed public record did not establish. Rights controls determine whether the site may link, paraphrase or exclude material.
Institutional control
CLM-0207 · interpretation
The case portfolio supports a modular permission stack controlled by different actors; no single regulator, utility, company or locality controls the full conversion chain.