Regional CohortPS-0004

Northern Virginia/NOVEC data-center cohort

Utility testimony reports served and contracted aggregates

MIXED / PROJECT-LEVEL STATE NOT SEPARABLEAggregate utility testimony

Executive evidence ceiling

What a decision maker may safely take from this record

Permitted reading

The record supports only the bounded status shown here: MIXED / PROJECT-LEVEL STATE NOT SEPARABLE. Utility testimony reports served and contracted aggregates

Not established

A single cohort-wide C-code, participant state, realized capacity, or project-level progression.

Owner attention

Project identity, meter basis, utilization, later updates

Geography
Northern Virginia
Object subtype
Utility Service Cohort
AI connection
Data-center cohort; AI-specific share unknown
Recorded figure
1,408 MW served; 3,513 MW contracted in cited testimony
Unit basis
Utility-reported aggregate; period and project mapping require extraction
Countable operating capacity
NO — aggregate cannot be converted to AI economic capacity

Conversion-chain position

C0–C21, without implied progression

Handling modeMIXED OR NONSEPARABLE

Explicitly represented in this record Not established by this record
  1. C0–C6

    Entry and permission

    1. C0 Concept or rumor
    2. C1 Public announcement
    3. C2 Site identified
    4. C3 Land option or negotiation
    5. C4 Land controlled
    6. C5 Zoning or land-use application
    7. C6 Zoning or land-use approval
  2. C7–C10

    Service-model fork

    1. C7 Utility service or interconnection request
    2. C8 Study or review accepted
    3. C9 Tariff or service pathway identified
    4. C10 Agreement executed or obligation recorded
  3. C11–C17

    Build and operation

    1. C11 Network, generation, or facility upgrades funded
    2. C12 Construction started
    3. C13 Major electrical and cooling equipment delivered
    4. C14 Grid or onsite supply energized
    5. C15 Facility commissioned
    6. C16 IT capacity installed
    7. C17 Compute cluster operating
  4. C18–C20

    Dark Zone

    1. C18 Contracted customer use observed
    2. C19 Utilization or revenue effect observed
    3. C20 Sustained economic compute capacity
  5. C21

    Changed status

    1. C21 Delayed, cancelled, downsized, superseded, or repurposed

Recorded position: MIXED / PROJECT-LEVEL STATE NOT SEPARABLE

Utility testimony reports served and contracted aggregates

No numbered C-state is assigned by this record. This preserves a forecast, framework, mixed, unknown or otherwise non-project boundary rather than forcing a false position.

State boundary

Scope-specific assertions

MIXED / PROJECT-LEVEL STATE NOT SEPARABLEAggregate utility testimony

No forced project state

Utility testimony reports served and contracted aggregates

Control rule

A single cohort-wide C-code, participant state, realized capacity, or project-level progression.

Four-register control

Figures stay in the register that produced them

No cross-register conversion is performed without an explicit source-stated bridge.

  1. R01Load

    Recorded, basis-bound

    1,408 MW served; 3,513 MW contracted in cited testimony

    Utility-reported aggregate; period and project mapping require extraction

  2. R02Supply

    No bridge inferred

    No supply-register quantity is normalized for this record.

    Project state is not treated as proof of deliverable, firm or operating supply.

  3. R03Money

    No bridge inferred

    No separate money-register metric is normalized for this record.

    Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.

  4. R04AI-share

    Not established

    Data-center cohort; AI-specific share unknown

    Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.

Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.

AI-share boundary

Broader infrastructure does not become AI-only by implication

Data-center cohort; AI-specific share unknown

01

Broader measured scope

Campus, data-center, portfolio, utility, accelerator or financial quantity.

Explicit source bridge

Named AI workload or customer scope · denominator · period · allocation method.

02

AI-attributable subset

Reportable only to the extent directly defined by the source.

AI-share not established

Without the bridge, retain the broader label and stop the attribution.

Control rule: GPU count, company narrative, total campus MW or portfolio capex does not supply an AI-share denominator on its own.

Atomic evidence stack

Claims retain their own ceiling, locator and sources

0 linked claims at the current cutoff.

No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.

Record stewardship

What is known, missing and capable of changing the record

Contrary evidenceNo linked test at cutoff

Absence of a linked item is not proof that contrary evidence does not exist.

Negative findingsNo linked negative finding

Continue to treat unknown information as unknown, not zero.

Reopen triggers1 active rule

A qualifying evidence delta requires review and rebuild.

What could change this record

  • OIR-0008 · New official demand forecast, project pipeline, operational-data accuracy report, or material project cancellation/energization is published.

    Required update: Add vintage rather than overwrite; reconcile project IDs; update state and double-counting register.

Source register

Trace the public record

1 linked source; rights and locators remain attached.

Source records

  1. SRC-0052 — NOVEC Evidence for Virginia Load Growth Technical Conference

    Virginia SCC docket / Northern Virginia Electric Cooperative · 2024-12-16 · Tier A-minus

    Locator: Testimony: 58 buildings; 1,408 MW served; 3,513 MW contracted

    PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE