Regional CohortPS-0034
AWS Madison County Mississippi original campus cohort
Amazon states two campuses were being developed
C12Two-campus cohortExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
Physical construction has begun for the specified scope. Amazon states two campuses were being developed
Not established
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Owner attention
Individual site states, phase progress, power, energization and spend reconciliation
- Geography
- Madison County, Mississippi
- Object subtype
- Two Campus Cohort
- AI connection
- AWS cloud/AI infrastructure context
- Recorded figure
- Prior $10B investment context; later statewide totals overlap
- Unit basis
- Portfolio capex, not capacity
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeEXACT PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: C12
Amazon states two campuses were being developed
State boundary
Scope-specific assertions
What this establishes
Physical construction has begun for the specified scope.
What this does not prove
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Not normalized
The tracker row carries a money-register figure (Prior $10B investment context; later statewide totals overlap); it is not treated as load.
No load quantity is imputed from money, supply, accelerator count or project state.
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money Recorded, basis-bound
Prior $10B investment context; later statewide totals overlap
Portfolio capex, not capacity
-
R04AI-share Source-bounded description
AWS cloud/AI infrastructure context
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
AWS cloud/AI infrastructure context
Atomic evidence stack
Claims retain their own ceiling, locator and sources
0 linked claims at the current cutoff.
No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.
Record stewardship
What is known, missing and capable of changing the record
Absence of a linked item is not proof that contrary evidence does not exist.
Continue to treat unknown information as unknown, not zero.
A qualifying evidence delta requires review and rebuild.
What could change this record
OIR-0019· Any bounded project receives a material cancellation, downsizing, land/permit decision, construction milestone, service agreement, energization, commissioning, phase redefinition, or portfolio-capacity reconciliation.Required update: Create dated state observation; preserve prior state; record supersession/overlap; update affected capacity fields without borrowing later-state language.
Source register
Trace the public record
2 linked sources; rights and locators remain attached.
Source records
-
SRC-0081— Amazon announces $3 billion Warren County, Mississippi data center investmentAmazon · 2025-01-23 · Tier A-minus
Locator: Warren County $3B plan; statement that two Madison County campuses were being developed
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
Mississippi Development Authority · 2026-04-09 · Tier A-minus
Locator: $11B Madison County expansion; $1B Clinton retrofit; $25B cumulative planned statewide statement
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE