Forecast ObjectPS-0003
PJM AEP-zone large-load forecast cohort
This is a screened PJM forecast object, not a project state or realized-load record.
Forecast — no project C-stateAggregate forecast cohortExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
Forecast method and vintage only; no project state, deliverable capacity or realization rate.
Not established
Any implied project progress or conversion-chain position.
Owner attention
Project-level mapping and realization
- Geography
- Ohio/PJM AEP zone
- Object subtype
- Regional Load Forecast
- AI connection
- Data-center/large-load category; AI share not established
- Recorded figure
- See 2026 forecast and FERC Figure 7
- Unit basis
- Forecast MW by year/zone
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeNO PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: Forecast — no project C-state
PJM screened forecast adjustment
No numbered C-state is assigned by this record. This preserves a forecast, framework, mixed, unknown or otherwise non-project boundary rather than forcing a false position.
State boundary
Scope-specific assertions
No forced project state
PJM screened forecast adjustment
Control rule
Any implied project progress or conversion-chain position.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Not normalized
See 2026 forecast and FERC Figure 7 is retained as a non-normalized or non-load figure; no MW conversion is performed.
No load quantity is imputed from money, supply, accelerator count or project state.
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Not established
Data-center/large-load category; AI share not established
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Data-center/large-load category; AI share not established
Atomic evidence stack
Claims retain their own ceiling, locator and sources
6 linked claims at the current cutoff.
CLM-0016 · forecast
PJM’s 2026 load forecast process screens large-load adjustment requests rather than automatically including the full requested amount.
- Claim ceiling
- Forecast-inclusion method, not validation of each included project.
- Evidence
- Tier A · HIGH
- Locator
- SRC-0029 methodology; SRC-0030 criteria; SRC-0031 slides 30–31
CLM-0017 · interpretation
Official 2026 records show that large-load forecasts can be materially revised downward after updated screening or assumptions, supporting the forecast-inflation rival as a live hypothesis.
- Claim ceiling
- Forecast-revision mechanism; no claim that all pipelines are inflated.
- Evidence
- Tier A · HIGH that revisions occur; MEDIUM on broader generalization
- Locator
- SRC-0012 pp. 9–10, Figure 7; PJM forecast and accuracy materials
CLM-0022 · implementation
Public records identify flexibility and conditional service as possible adaptation mechanisms, but current evidence does not justify treating all AI data-center load as flexible.
- Claim ceiling
- Mechanism availability/hypothesis; no universal technical capability or customer commitment.
- Evidence
- Tier A · MEDIUM
- Locator
- FERC State of Markets Figure 8; SPP ER26-1323; Virginia conference/testimony
CLM-0025 · interpretation
Available national and regional public records use incompatible vintages, geographic boundaries, and state definitions; quantitative consolidation requires raw-value preservation and explicit normalization.
- Claim ceiling
- Methodological conclusion; no merged national project total in Pass 01.
- Evidence
- Tier A · HIGH
- Locator
- Methods and vintages identified in each source
CLM-0032 · interpretation
FERC staff reported more than 50 GW of U.S. data-center capacity in service at the end of 2025 and a 24% CAGR since 2020, but the public report relies on a proprietary Yes Energy database whose project-level state definitions are not fully auditable in the public record.
- Claim ceiling
- External source-defined benchmark; not additive to the Pass 02 project ledger and not a C14–C20 audit.
- Evidence
- Tier A · HIGH that FERC reported the values; MEDIUM-LOW for state reconciliation
- Locator
- PDF p. 9 (report p. 7), Figure 5 and note 14
- Linked sources
SRC-0012
CLM-0033 · interpretation
TWh/year, equivalent average GW, source-defined facility capacity, system peak GW, requested load, design capacity, MW-IT, GPU count, and announced capex are non-interchangeable metrics and are held in separate comparable groups.
- Claim ceiling
- Normalization rule; no conversion beyond explicit formula and assumptions.
- Evidence
- Tier A + CONTROLLING INPUT · HIGH
- Locator
- Operating Prompt §§7–8; Seed Charter §§3,6; quantitative source locators in Pass 02 ledgers
Record stewardship
What is known, missing and capable of changing the record
Review rival propositions before strengthening the claim.
These searches bound what the public record did not establish.
A qualifying evidence delta requires review and rebuild.
Contrary evidence and rival tests
CTR-0001 · Forecast inflation
Requested and announced pipelines can materially exceed screened forecasts or realized load.
Evidence result:PJM differentiates utility demand asks from preliminary/final included adjustments; FERC reported a 15% lower 2032 AEP-zone forecast versus the prior vintage after large-load adjustments.
Ceiling effect:No pipeline-to-realization conversion; preserve vintage and screening.
CTR-0003 · Flexible-load response
Some computational loads may curtail, shift, or accept conditional service, reducing some system constraints.
Evidence result:FERC identifies flexible crypto-mining behavior as illustrative; SPP filed conditional HILL service; Virginia convened a flexibility record. Transferability to AI loads is unproven.
Ceiling effect:Possible mechanism only; not universal capability or solved reliability risk.
CTR-0008 · Policy and data uncertainty
Evolving rules, changing forecast vintages, and inconsistent definitions may be a principal planning and evidentiary cost.
Evidence result:FERC, NERC, PJM, ERCOT, and state records are contemporaneously changing and use different units/states.
Ceiling effect:Every current claim requires cutoff and reopen trigger.
CTR-0013 · Registry and methodology opacity
A source-defined national in-service estimate may not reconcile to a public C0–C20 project audit.
Evidence result:FERC’s >50 GW value rests on proprietary Yes Energy data; no unified official project-state registry was located.
Ceiling effect:Benchmark cannot be added to or used to validate every project row.
Public-record gaps
NEG-0001
Question checked:Is there a unified official U.S. registry of AI/data-center projects with state-normalized capacity?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED; no unified registry identified.
Implication:Build project crosswalk; no national pipeline total.
NEG-0006
Question checked:Is there a standardized national public record for commissioning and utilization?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED.
Implication:Require project-specific C15–C20 evidence.
NEG-0008
Question checked:Can computational-load flexibility be generalized from crypto mining to AI data centers?
No sufficient public evidence located for a universal generalization.
Implication:Case-specific, measured claim only.
What could change this record
OIR-0008· New official demand forecast, project pipeline, operational-data accuracy report, or material project cancellation/energization is published.Required update: Add vintage rather than overwrite; reconcile project IDs; update state and double-counting register.
OIR-0009· A public field demonstration or binding service agreement provides measured AI/computational-load flexibility evidence.Required update: Capture workload, baseline, response speed/duration, customer constraints, sample, and transferability limits.
OIR-0017· A new official national or regional demand forecast, AEO/LBNL update, or method revision changes scope, horizon, scenario range, or unit bridge.Required update: Add new vintage without deleting prior; reconcile scope, method, denominator and supersession; rerun normalization.
OIR-0018· A reproducible public methodology or project-level dataset becomes available for the FERC/Yes Energy in-service capacity series.Required update: Inspect definitions, coverage, duplicates and state thresholds; reconcile with C0–C20 and revise benchmark ceiling.
Source register
Trace the public record
3 linked sources; rights and locators remain attached.
Source records
-
SRC-0012— 2025 State of the Markets ReportFederal Energy Regulatory Commission, Office of Enforcement · 2026-03-26 · Tier A
Locator: PDF pp. 9–10 (report pp. 7–8), Figure 5 and note 14; other market-review figures as separately cited
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0029— 2026 PJM Load Forecast ReportPJM Interconnection · 2026-01-14 · Tier A
Locator: Executive summary; large-load adjustment methodology; zone tables
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0032— Load Forecast Accuracy Report — May 2026PJM Interconnection · 2026-05-29 · Tier A
Locator: Overview p. 3; operational-data comparisons
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE