ProjectPS-0022
Meta El Paso data center
Company portfolio update lists project under construction
C12Named site under constructionExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
Physical construction has begun for the specified scope. Company portfolio update lists project under construction
Not established
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Owner attention
Site-specific power basis, construction milestones, energization and commissioning
- Geography
- El Paso, Texas
- Object subtype
- Named Site
- AI connection
- Meta AI infrastructure context; site-specific AI share not quantified
- Recorded figure
- At least 1 GW future-site phrase may apply; site allocation/basis not established
- Unit basis
- Basis unspecified; no capacity counted
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeEXACT PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: C12
Company portfolio update lists project under construction
State boundary
Scope-specific assertions
What this establishes
Physical construction has begun for the specified scope.
What this does not prove
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Recorded, basis-bound
At least 1 GW future-site phrase may apply; site allocation/basis not established
Basis unspecified; no capacity counted
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Source-bounded description
Meta AI infrastructure context; site-specific AI share not quantified
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Meta AI infrastructure context; site-specific AI share not quantified
Atomic evidence stack
Claims retain their own ceiling, locator and sources
0 linked claims at the current cutoff.
No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.
Record stewardship
What is known, missing and capable of changing the record
Absence of a linked item is not proof that contrary evidence does not exist.
Continue to treat unknown information as unknown, not zero.
A qualifying evidence delta requires review and rebuild.
What could change this record
OIR-0019· Any bounded project receives a material cancellation, downsizing, land/permit decision, construction milestone, service agreement, energization, commissioning, phase redefinition, or portfolio-capacity reconciliation.Required update: Create dated state observation; preserve prior state; record supersession/overlap; update affected capacity fields without borrowing later-state language.
Source register
Trace the public record
1 linked source; rights and locators remain attached.
Source records
-
SRC-0069— Infrastructure Explained: Meta Data CentersMeta · 2026-04-28 · Tier A-minus
Locator: Richland Parish, Lebanon, El Paso and Tulsa construction status; selected future-site capacity statements
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE