ProjectPS-0026
Google Mesa data center
Current company locations page says in development after historical 2025 operational target
Multiple exact scoped state assertions; no flattened badgeNamed siteExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
The record supports only the bounded status shown here: Multiple exact scoped state assertions; no flattened badge. Current company locations page says in development after historical 2025 operational target
Not established
A secured site, land control, zoning, utility request, approved service, agreement, funded upgrade, construction, energized power, operation, utilization, or economic capacity.
Owner attention
Cause, revised completion date, construction/energization milestones and site load
- Geography
- Mesa, Arizona
- Object subtype
- Named Site With Adverse Status
- AI connection
- Google compute infrastructure; AI-specific share not public in inspected sources
- Recorded figure
- No normalized public power quantity
- Unit basis
- No capacity counted
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeCOMPOSITE SCOPED
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: Multiple exact scoped state assertions; no flattened badge
Current company locations page says in development after historical 2025 operational target
State boundary
Scope-specific assertions
What this establishes
Physical construction has begun for the specified scope.
What this does not prove
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
What this establishes
An adverse or changed-status subtype is evidenced for the specified scope and date.
What this does not prove
A universal terminal state, erasure of historical states, final cancellation when only delay/appeal is shown, or failure of related phases/projects.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Not normalized
No normalized public power quantity is retained as a non-normalized or non-load figure; no MW conversion is performed.
No load quantity is imputed from money, supply, accelerator count or project state.
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Source-bounded description
Google compute infrastructure; AI-specific share not public in inspected sources
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Google compute infrastructure; AI-specific share not public in inspected sources
Atomic evidence stack
Claims retain their own ceiling, locator and sources
0 linked claims at the current cutoff.
No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.
Record stewardship
What is known, missing and capable of changing the record
Absence of a linked item is not proof that contrary evidence does not exist.
Continue to treat unknown information as unknown, not zero.
A qualifying evidence delta requires review and rebuild.
What could change this record
OIR-0021· Google updates Mesa to operating, cancels/downsides it, supplies a revised date, or a public primary record establishes the cause of delay.Required update: Add new dated state; distinguish objective, current implementation and cause; do not infer causation from chronology.
Source register
Trace the public record
2 linked sources; rights and locators remain attached.
Source records
-
SRC-0073— Locations of Google Data CentersGoogle · CONTINUOUSLY UPDATED — CURRENT PAGE · Tier A-minus
Locator: North America list: Mesa, Arizona marked in development; Jackson County, Alabama listed without in-development marker
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0074— Google announces carbon-free energy plan for Mesa data centerGoogle · 2024-03-14 · Tier A-minus
Locator: Historical objective that Mesa data center was expected to be operational in 2025
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE