ProjectPS-0036

Vantage Lighthouse campus

Wisconsin DNR states campus is under construction; multiple permits/plans documented

C12Named campus

Executive evidence ceiling

What a decision maker may safely take from this record

Permitted reading

Physical construction has begun for the specified scope. Wisconsin DNR states campus is under construction; multiple permits/plans documented

Not established

Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.

Owner attention

Electrical delivery, occupancy, commissioning, IT installation, customer use and utilization

Geography
Port Washington, Wisconsin
Object subtype
Named Campus
AI connection
Data-center campus; AI-specific use not established
Recorded figure
No public operating MW normalized
Unit basis
Construction/permit state; land area not capacity
Countable operating capacity
NO

Conversion-chain position

C0–C21, without implied progression

Handling modeEXACT PROJECT STATE

Explicitly represented in this record Not established by this record
  1. C0–C6

    Entry and permission

    1. C0 Concept or rumor
    2. C1 Public announcement
    3. C2 Site identified
    4. C3 Land option or negotiation
    5. C4 Land controlled
    6. C5 Zoning or land-use application
    7. C6 Zoning or land-use approval
  2. C7–C10

    Service-model fork

    1. C7 Utility service or interconnection request
    2. C8 Study or review accepted
    3. C9 Tariff or service pathway identified
    4. C10 Agreement executed or obligation recorded
  3. C11–C17

    Build and operation

    1. C11 Network, generation, or facility upgrades funded
    2. C12 Construction started
    3. C13 Major electrical and cooling equipment delivered
    4. C14 Grid or onsite supply energized
    5. C15 Facility commissioned
    6. C16 IT capacity installed
    7. C17 Compute cluster operating
  4. C18–C20

    Dark Zone

    1. C18 Contracted customer use observed
    2. C19 Utilization or revenue effect observed
    3. C20 Sustained economic compute capacity
  5. C21

    Changed status

    1. C21 Delayed, cancelled, downsized, superseded, or repurposed

Recorded position: C12

Wisconsin DNR states campus is under construction; multiple permits/plans documented

State boundary

Scope-specific assertions

C12Construction startedNamed campus

What this establishes

Physical construction has begun for the specified scope.

What this does not prove

Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.

Four-register control

Figures stay in the register that produced them

No cross-register conversion is performed without an explicit source-stated bridge.

  1. R01Load

    Not normalized

    No public operating MW normalized is retained as a non-normalized or non-load figure; no MW conversion is performed.

    No load quantity is imputed from money, supply, accelerator count or project state.

  2. R02Supply

    No bridge inferred

    No supply-register quantity is normalized for this record.

    Project state is not treated as proof of deliverable, firm or operating supply.

  3. R03Money

    No bridge inferred

    No separate money-register metric is normalized for this record.

    Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.

  4. R04AI-share

    Not established

    Data-center campus; AI-specific use not established

    Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.

Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.

AI-share boundary

Broader infrastructure does not become AI-only by implication

Data-center campus; AI-specific use not established

01

Broader measured scope

Campus, data-center, portfolio, utility, accelerator or financial quantity.

Explicit source bridge

Named AI workload or customer scope · denominator · period · allocation method.

02

AI-attributable subset

Reportable only to the extent directly defined by the source.

AI-share not established

Without the bridge, retain the broader label and stop the attribution.

Control rule: GPU count, company narrative, total campus MW or portfolio capex does not supply an AI-share denominator on its own.

Atomic evidence stack

Claims retain their own ceiling, locator and sources

0 linked claims at the current cutoff.

No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.

Record stewardship

What is known, missing and capable of changing the record

Contrary evidenceNo linked test at cutoff

Absence of a linked item is not proof that contrary evidence does not exist.

Negative findingsNo linked negative finding

Continue to treat unknown information as unknown, not zero.

Reopen triggers1 active rule

A qualifying evidence delta requires review and rebuild.

What could change this record

  • OIR-0038 · Vantage Lighthouse receives occupancy/commissioning evidence or material permit/service change.

    Required update: Update permission, energization, commissioning and operating states separately.

Source register

Trace the public record

1 linked source; rights and locators remain attached.

Source records

  1. SRC-0133 — Port Washington Data Center Proposal — Vantage Lighthouse

    Wisconsin Department of Natural Resources · 2026-06-12 · Tier A

    Locator: Construction, air permits, sewer service, water/sewer plans, WEPA sections

    PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE