ProjectPS-0036
Vantage Lighthouse campus
Wisconsin DNR states campus is under construction; multiple permits/plans documented
C12Named campusExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
Physical construction has begun for the specified scope. Wisconsin DNR states campus is under construction; multiple permits/plans documented
Not established
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Owner attention
Electrical delivery, occupancy, commissioning, IT installation, customer use and utilization
- Geography
- Port Washington, Wisconsin
- Object subtype
- Named Campus
- AI connection
- Data-center campus; AI-specific use not established
- Recorded figure
- No public operating MW normalized
- Unit basis
- Construction/permit state; land area not capacity
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeEXACT PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: C12
Wisconsin DNR states campus is under construction; multiple permits/plans documented
State boundary
Scope-specific assertions
What this establishes
Physical construction has begun for the specified scope.
What this does not prove
Equipment delivery, completed facility, energization, commissioning, IT installation, cluster operation, customer use, utilization/revenue, or economic capacity.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Not normalized
No public operating MW normalized is retained as a non-normalized or non-load figure; no MW conversion is performed.
No load quantity is imputed from money, supply, accelerator count or project state.
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Not established
Data-center campus; AI-specific use not established
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Data-center campus; AI-specific use not established
Atomic evidence stack
Claims retain their own ceiling, locator and sources
0 linked claims at the current cutoff.
No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.
Record stewardship
What is known, missing and capable of changing the record
Absence of a linked item is not proof that contrary evidence does not exist.
Continue to treat unknown information as unknown, not zero.
A qualifying evidence delta requires review and rebuild.
What could change this record
OIR-0038· Vantage Lighthouse receives occupancy/commissioning evidence or material permit/service change.Required update: Update permission, energization, commissioning and operating states separately.
Source register
Trace the public record
1 linked source; rights and locators remain attached.
Source records
-
SRC-0133— Port Washington Data Center Proposal — Vantage LighthouseWisconsin Department of Natural Resources · 2026-06-12 · Tier A
Locator: Construction, air permits, sewer service, water/sewer plans, WEPA sections
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE