Project Campus Or PhasePS-0001
Susquehanna / AWS Data Campus contractual power arrangement
Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established
C10 ceilingNamed campus / generation-customer contractual recordExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
A specified agreement or binding obligation is evidenced. Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established
Not established
Physical delivery, firm/deliverable service beyond the instrument, funded or completed upgrades, construction, energization, commissioning, operation, use, utilization, or economic capacity.
Owner attention
Detailed delivery profile, campus energization, utilization and economics not public
- Geography
- Pennsylvania / PJM
- Object subtype
- Contractual Power Arrangement
- AI connection
- Documented as data-center/AI-related in FERC record context
- Recorded figure
- Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042
- Unit basis
- Contractual maximum MW under different arrangements/vintages; not energized or average load
- Countable operating capacity
- NO
Conversion-chain position
C0–C21, without implied progression
Handling modeEXACT PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: C10 ceiling
Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established
Signature model · C7–C10
One state vocabulary, five non-transferable service pathways
Each row requires its own authority, instrument, scope and evidence. A state or capacity measure cannot be borrowed from another row.
-
R Retail large-load service
Utility · state commission
- C7
Service request
- C8
Accepted utility review
- C9
Tariff or service class
- C10
Executed service obligation
-
T Transmission service
Transmission provider · RTO/ISO · FERC
- C7
Transmission request
- C8
Accepted system study
- C9
Transmission tariff path
- C10
Executed service obligation
-
G Generator interconnection
Interconnecting utility · RTO/ISO
- C7
Interconnection request
- C8
Accepted study stage
- C9
Interconnection tariff path
- C10
Executed agreement or obligation
-
C Co-location
Facility owner · utility · relevant regulator
- C7
Arrangement request
- C8
Technical or regulatory review
- C9
Applicable co-location path
- C10
Executed facility-specific obligation
-
B Behind the meter
Site owner · utility · local/state authority
- C7
On-site arrangement request
- C8
Engineering or compliance review
- C9
Ownership and service path
- C10
Executed on-site obligations
State boundary
Scope-specific assertions
What this establishes
A specified agreement or binding obligation is evidenced.
What this does not prove
Physical delivery, firm/deliverable service beyond the instrument, funded or completed upgrades, construction, energization, commissioning, operation, use, utilization, or economic capacity.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Not normalized
The tracker row carries a supply-register figure (Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042); it is not treated as load.
No load quantity is imputed from money, supply, accelerator count or project state.
-
R02Supply Recorded, instrument-bound
Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042
The quantity remains attached to its PPA, contracted-power or service-instrument basis; it is not energized or utilized load.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Source-bounded description
Documented as data-center/AI-related in FERC record context
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Documented as data-center/AI-related in FERC record context
Atomic evidence stack
Claims retain their own ceiling, locator and sources
0 linked claims at the current cutoff.
No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.
Record stewardship
What is known, missing and capable of changing the record
Absence of a linked item is not proof that contrary evidence does not exist.
Continue to treat unknown information as unknown, not zero.
A qualifying evidence delta requires review and rebuild.
What could change this record
OIR-0051· Talen or AWS discloses delivery commencement, revised PPA quantity, regulatory change, campus energization or termination affecting the 1,920 MW arrangement.Required update: Separate contract amendment, generation delivery, grid service, campus energization and operating load.
Source register
Trace the public record
3 linked sources; rights and locators remain attached.
Source records
-
Federal Energy Regulatory Commission · 2024-11-01 · Tier A
Locator: 189 FERC ¶ 61,078; pp. 5–7; paras. 6–11; ordering paragraphs
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0010— FERC Directs PJM to Create New Rules for Co-Located Large LoadsFederal Energy Regulatory Commission · 2025-12-18 · Tier A-minus
Locator: Docket EL25-49-000; official order summary
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0161— Talen Energy Corporation — Quarterly Report on Form 10-Q for quarter ended March 31, 2026Talen Energy Corporation · 2026-05-05 · Tier A
Locator: Glossary lines 2053–2056; revised AWS PPA up to 1,920 MW through 2042; transition in April 2026
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE