Project Campus Or PhasePS-0001

Susquehanna / AWS Data Campus contractual power arrangement

Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established

C10 ceilingNamed campus / generation-customer contractual record

Executive evidence ceiling

What a decision maker may safely take from this record

Permitted reading

A specified agreement or binding obligation is evidenced. Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established

Not established

Physical delivery, firm/deliverable service beyond the instrument, funded or completed upgrades, construction, energization, commissioning, operation, use, utilization, or economic capacity.

Owner attention

Detailed delivery profile, campus energization, utilization and economics not public

Geography
Pennsylvania / PJM
Object subtype
Contractual Power Arrangement
AI connection
Documented as data-center/AI-related in FERC record context
Recorded figure
Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042
Unit basis
Contractual maximum MW under different arrangements/vintages; not energized or average load
Countable operating capacity
NO

Conversion-chain position

C0–C21, without implied progression

Handling modeEXACT PROJECT STATE

Explicitly represented in this record Not established by this record
  1. C0–C6

    Entry and permission

    1. C0 Concept or rumor
    2. C1 Public announcement
    3. C2 Site identified
    4. C3 Land option or negotiation
    5. C4 Land controlled
    6. C5 Zoning or land-use application
    7. C6 Zoning or land-use approval
  2. C7–C10

    Service-model fork

    1. C7 Utility service or interconnection request
    2. C8 Study or review accepted
    3. C9 Tariff or service pathway identified
    4. C10 Agreement executed or obligation recorded
  3. C11–C17

    Build and operation

    1. C11 Network, generation, or facility upgrades funded
    2. C12 Construction started
    3. C13 Major electrical and cooling equipment delivered
    4. C14 Grid or onsite supply energized
    5. C15 Facility commissioned
    6. C16 IT capacity installed
    7. C17 Compute cluster operating
  4. C18–C20

    Dark Zone

    1. C18 Contracted customer use observed
    2. C19 Utilization or revenue effect observed
    3. C20 Sustained economic compute capacity
  5. C21

    Changed status

    1. C21 Delayed, cancelled, downsized, superseded, or repurposed

Recorded position: C10 ceiling

Revised front-of-the-meter AWS PPA transitioned April 2026; physical delivery and campus operation not established

Signature model · C7–C10

One state vocabulary, five non-transferable service pathways

Each row requires its own authority, instrument, scope and evidence. A state or capacity measure cannot be borrowed from another row.

  1. R

    Retail large-load service

    Utility · state commission

    1. C7

      Service request

    2. C8

      Accepted utility review

    3. C9

      Tariff or service class

    4. C10

      Executed service obligation

  2. T

    Transmission service

    Transmission provider · RTO/ISO · FERC

    1. C7

      Transmission request

    2. C8

      Accepted system study

    3. C9

      Transmission tariff path

    4. C10

      Executed service obligation

  3. G

    Generator interconnection

    Interconnecting utility · RTO/ISO

    1. C7

      Interconnection request

    2. C8

      Accepted study stage

    3. C9

      Interconnection tariff path

    4. C10

      Executed agreement or obligation

  4. C

    Co-location

    Facility owner · utility · relevant regulator

    1. C7

      Arrangement request

    2. C8

      Technical or regulatory review

    3. C9

      Applicable co-location path

    4. C10

      Executed facility-specific obligation

  5. B

    Behind the meter

    Site owner · utility · local/state authority

    1. C7

      On-site arrangement request

    2. C8

      Engineering or compliance review

    3. C9

      Ownership and service path

    4. C10

      Executed on-site obligations

Reading rule: C7–C10 records process evidence, not inevitable progression. Exact procedures vary by jurisdiction and service model; C10 still does not establish physical delivery or operating load.

State boundary

Scope-specific assertions

C10Agreement executed or obligation recordedNamed campus / generation-customer contractual record

What this establishes

A specified agreement or binding obligation is evidenced.

What this does not prove

Physical delivery, firm/deliverable service beyond the instrument, funded or completed upgrades, construction, energization, commissioning, operation, use, utilization, or economic capacity.

Four-register control

Figures stay in the register that produced them

No cross-register conversion is performed without an explicit source-stated bridge.

  1. R01Load

    Not normalized

    The tracker row carries a supply-register figure (Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042); it is not treated as load.

    No load quantity is imputed from money, supply, accelerator count or project state.

  2. R02Supply

    Recorded, instrument-bound

    Earlier ISA context up to 150 MW behind each of two units; revised AWS PPA up to 1,920 MW through 2042

    The quantity remains attached to its PPA, contracted-power or service-instrument basis; it is not energized or utilized load.

  3. R03Money

    No bridge inferred

    No separate money-register metric is normalized for this record.

    Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.

  4. R04AI-share

    Source-bounded description

    Documented as data-center/AI-related in FERC record context

    Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.

Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.

AI-share boundary

Broader infrastructure does not become AI-only by implication

Documented as data-center/AI-related in FERC record context

01

Broader measured scope

Campus, data-center, portfolio, utility, accelerator or financial quantity.

Explicit source bridge

Named AI workload or customer scope · denominator · period · allocation method.

02

AI-attributable subset

Reportable only to the extent directly defined by the source.

Source-bounded AI description

Without the bridge, retain the broader label and stop the attribution.

Control rule: GPU count, company narrative, total campus MW or portfolio capex does not supply an AI-share denominator on its own.

Atomic evidence stack

Claims retain their own ceiling, locator and sources

0 linked claims at the current cutoff.

No atomic claim is linked to this tracker row. Do not strengthen the row from surrounding context.

Record stewardship

What is known, missing and capable of changing the record

Contrary evidenceNo linked test at cutoff

Absence of a linked item is not proof that contrary evidence does not exist.

Negative findingsNo linked negative finding

Continue to treat unknown information as unknown, not zero.

Reopen triggers1 active rule

A qualifying evidence delta requires review and rebuild.

What could change this record

  • OIR-0051 · Talen or AWS discloses delivery commencement, revised PPA quantity, regulatory change, campus energization or termination affecting the 1,920 MW arrangement.

    Required update: Separate contract amendment, generation delivery, grid service, campus energization and operating load.

Source register

Trace the public record

3 linked sources; rights and locators remain attached.

Source records

  1. SRC-0008 — Order Rejecting Amended Interconnection Service Agreement, Susquehanna Nuclear, LLC et al.

    Federal Energy Regulatory Commission · 2024-11-01 · Tier A

    Locator: 189 FERC ¶ 61,078; pp. 5–7; paras. 6–11; ordering paragraphs

    PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE

  2. SRC-0010 — FERC Directs PJM to Create New Rules for Co-Located Large Loads

    Federal Energy Regulatory Commission · 2025-12-18 · Tier A-minus

    Locator: Docket EL25-49-000; official order summary

    PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE

  3. SRC-0161 — Talen Energy Corporation — Quarterly Report on Form 10-Q for quarter ended March 31, 2026

    Talen Energy Corporation · 2026-05-05 · Tier A

    Locator: Glossary lines 2053–2056; revised AWS PPA up to 1,920 MW through 2042; transition in April 2026

    PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE