Project Campus Or PhasePS-0012
Stargate I / Crusoe Abilene initial phase
Company disclosures support C17 for the initial two-building phase; measured operating power and C18–C20 remain unestablished.
C17Initial two-building phaseExecutive evidence ceiling
What a decision maker may safely take from this record
Permitted reading
C17 company assertion for the initial phase; no countable operating MW and no C18–C20.
Not established
Measured operating MW, customer use, utilization, revenue, profitability, sustained economic capacity, or operation of every phase.
Owner attention
Measured load, installed IT quantity, utilization, customer use, revenue/economic output
- Geography
- Abilene area, Taylor County, Texas
- Object subtype
- Initial Operating Phase
- AI connection
- Directly documented AI training and inference
- Recorded figure
- 200+ MW design for initial phase; current operating MW unknown
- Unit basis
- Facility design power, not measured operating/average/IT load
- Countable operating capacity
- UNKNOWN — PUBLIC EVIDENCE NOT LOCATED
Conversion-chain position
C0–C21, without implied progression
Handling modeEXACT PROJECT STATE
-
C0–C6
Entry and permission
- C0 Concept or rumor
- C1 Public announcement
- C2 Site identified
- C3 Land option or negotiation
- C4 Land controlled
- C5 Zoning or land-use application
- C6 Zoning or land-use approval
-
C7–C10
Service-model fork
- C7 Utility service or interconnection request
- C8 Study or review accepted
- C9 Tariff or service pathway identified
- C10 Agreement executed or obligation recorded
-
C11–C17
Build and operation
- C11 Network, generation, or facility upgrades funded
- C12 Construction started
- C13 Major electrical and cooling equipment delivered
- C14 Grid or onsite supply energized
- C15 Facility commissioned
- C16 IT capacity installed
- C17 Compute cluster operating
-
C18–C20
Dark Zone
- C18 Contracted customer use observed
- C19 Utilization or revenue effect observed
- C20 Sustained economic compute capacity
-
C21
Changed status
- C21 Delayed, cancelled, downsized, superseded, or repurposed
Recorded position: C17
Company states two buildings energized, racks installed and early training/inference workloads running
Signature model · C17–C20
The evidence boundary becomes less observable after operation
The gradient represents public-record visibility, not the existence or absence of private activity.
- C17Threshold observation
Operating infrastructure
A bounded operating statement or equivalent observation.
Boundary: Does not establish customer use, utilization or project economics.
- C18Commercial bridge
Contracted use
A scoped arrangement linking operating capacity to customer use.
Boundary: Contract scope, customer identity or capacity denominator may remain private.
- C19Measured downstream use
Utilization or revenue
A comparable measure with denominator, period and project scope.
Boundary: Portfolio or company-wide metrics may not isolate the named project.
- C20Durable operating-economic bridge
Sustained economic capacity
Evidence connecting sustained operation, use and economic output.
Boundary: Public project-level evidence is often absent or non-comparable.
Unknown is not zero. Missing public C18–C20 evidence is recorded as a scoped gap, not as proof of full utilization, failure or stranded capacity.
State boundary
Scope-specific assertions
What this establishes
The company describes the specified initial compute phase as energized, with racks installed and early training and inference workloads running.
What this does not prove
- Measured operating MW, average load, MW-IT, contracted customer use, sustained utilization, revenue, profitability, C18, C19, C20 or operation of the full 1.2 GW campus.
Four-register control
Figures stay in the register that produced them
No cross-register conversion is performed without an explicit source-stated bridge.
-
R01Load Recorded, basis-bound
200+ MW design for initial phase; current operating MW unknown
Facility design power, not measured operating/average/IT load
-
R02Supply No bridge inferred
No supply-register quantity is normalized for this record.
Project state is not treated as proof of deliverable, firm or operating supply.
-
R03Money No bridge inferred
No separate money-register metric is normalized for this record.
Capex, contract value, backlog, RPO, revenue and utilization are not converted into capacity or operating state.
-
R04AI-share Source-bounded description
Directly documented AI training and inference
Total data-center, campus or portfolio measures remain broader than AI unless the source provides an explicit AI-share boundary.
Aggregation policy: Not summable in this edition. No total, rank or realization percentage is generated.
AI-share boundary
Broader infrastructure does not become AI-only by implication
Directly documented AI training and inference
Non-summable metrics
Recorded figures and their basis
Each figure keeps its own unit, state, geography, vintage and caveat. No total is calculated.
200+ MW design for initial phase; current operating MW unknown
- Basis
- Facility design power
- State basis
- C17 initial phase; design figure is not measured operating load
- Geography
- Abilene area, Taylor County, Texas
- Vintage
- 2025 company disclosures
- Caveat
- Design power is not energized, average, peak, MW-IT, utilization or countable operating capacity.
Atomic evidence stack
Claims retain their own ceiling, locator and sources
11 linked claims at the current cutoff.
CLM-0039 · operational state
Crusoe states the first two Abilene buildings were energized, racks began arriving in June 2025, and early training and inference workloads were running; this supports C17 for the initial phase, while public measured operating MW, utilization, customer-use state, and sustained economics remain unknown.
- Claim ceiling
- C17 company assertion for initial phase; no countable operating MW and no C18–C20.
- Evidence
- Tier A-minus · MEDIUM-HIGH for company-disclosed C17; LOW for quantity and C18–C20
- Locator
- Live announcement operating-state paragraphs; expansion page total/phase description
CLM-0040 · interpretation
OpenAI’s five-site Stargate announcement states a portfolio approaching 7 GW planned capacity, while Crusoe describes Abilene as a 1.2 GW total campus design; these are overlapping, mixed-state company figures and cannot be summed as independent operating capacity.
- Claim ceiling
- Company planned/design portfolio values only; no aggregate energized or operating capacity.
- Evidence
- Tier A-minus · HIGH for disclosure overlap risk; LOW for site allocation
- Locator
- Stargate site and portfolio capacity statements; Abilene total campus statement
CLM-0051 · interpretation
No project in the bounded Pass 02 sample has public evidence sufficient to classify sustained economic compute capacity at C20, and no aggregate operating MW is reported because supported C17 states lack a common measured quantity.
- Claim ceiling
- UNKNOWN — PUBLIC EVIDENCE NOT LOCATED for C20 and aggregate operating MW; unknown is not zero.
- Evidence
- Tier A-minus · HIGH for bounded public-record sample; not a claim about confidential reality
- Locator
- Company operating-state disclosures; missing public utilization/economic metrics recorded in gap and quality registers
CLM-0052 · implementation
The four bounded records reaching C17—Abilene initial phase, Meta Kansas City, xAI Colossus, and Google Jackson County existing campus—are supported by interested-party company disclosures; Pass 02 records their states but does not treat them as independent causal, utilization, customer-use, revenue, or measured-load evidence.
- Claim ceiling
- C17 interested-party assertions only; no C18–C20 or operating-MW aggregation.
- Evidence
- Tier A-minus · HIGH for source-function classification; MEDIUM for C17 states
- Locator
- Named company operating disclosures
CLM-0146 · operational state
Crusoe’s Abilene company disclosures support C17 for an initial phase because two buildings were described as energized, racks installed and early workloads running.
- Claim ceiling
- Mechanism/state evidence only; no stronger project, operating, utilization or economic inference without separate public proof.
- Evidence
- Tier A-minus · MEDIUM-HIGH
- Locator
- See Pass 06 report and pass-specific ledgers for page/section locators
CLM-0147 · interpretation
The inspected Abilene disclosures do not establish public C18–C20 customer use, utilization, revenue attribution or sustained economic compute capacity.
- Claim ceiling
- Mechanism/state evidence only; no stronger project, operating, utilization or economic inference without separate public proof.
- Evidence
- Tier A-minus · HIGH
- Locator
- See Pass 06 report and pass-specific ledgers for page/section locators
CLM-0154 · interpretation
No inspected Pass 06 project record provides public evidence sufficient for C20 sustained economic compute capacity.
- Claim ceiling
- Mechanism/state evidence only; no stronger project, operating, utilization or economic inference without separate public proof.
- Evidence
- Tier A-minus · HIGH
- Locator
- See Pass 06 report and pass-specific ledgers for page/section locators
CLM-0188 · interpretation
No inspected public filing establishes C20 sustained economic compute capacity for a named AI data-center project.
- Claim ceiling
- Company portfolio revenue or backlog cannot substitute for named-site C20 proof.
- Evidence
- Tier A · HIGH
- Locator
- Operating, contractual and financial disclosures inspected through cutoff
CLM-0195 · implementation
The ERCOT aggregate cohort remains at C7, while the Abilene initial phase may be recorded separately at company-asserted C17; aggregate and named-project states must not be blended.
- Claim ceiling
- No measured operating MW, utilization, customer-use or C20 conclusion for Abilene.
- Evidence
- Tier A-minus · HIGH separation / MEDIUM-HIGH named state
- Locator
- ERCOT aggregate status; Crusoe operating/buildout disclosures
CLM-0205 · interpretation
At least five rival theses win materially across the selected portfolio: forecast inflation/screening, policy and data uncertainty, partial private-risk allocation, local veto/process risk and demand-quality limits.
- Claim ceiling
- Rival wins are mechanism-specific and do not generalize to all U.S. projects.
- Evidence
- Tier A · HIGH for bounded portfolio findings
- Locator
- Selected case evidence and PASS_08_RIVAL_WIN_REGISTER.csv
CLM-0206 · interpretation
No selected case reaches public C20 sustained economic compute capacity at cutoff.
- Claim ceiling
- Absence of public C20 proof is not proof that no private economic capacity exists.
- Evidence
- Tier A · HIGH
- Locator
- Case reachability profiles and named project disclosures
Record stewardship
What is known, missing and capable of changing the record
Review rival propositions before strengthening the claim.
These searches bound what the public record did not establish.
A qualifying evidence delta requires review and rebuild.
Contrary evidence and rival tests
CTR-0016 · Demand-quality and source-interest problem
Announcements, design values, accelerator counts and company operating statements do not establish measured load, utilization, customer use or sustained economic output.
Evidence result:Bounded project records contain C17 company assertions but lack a common public operating-MW or C18–C20 measure.
Ceiling effect:No aggregate operating MW and no C20 claim.
CTR-0039 · Non-power bottlenecks
Equipment manufacture, testing, transport and commissioning can bind after a power pathway exists.
Evidence result:DOE transformer and commissioning records separate these states.
Ceiling effect:No power-only causal claim.
CTR-0040 · Supply response
Manufacturers are investing in new transformer and distribution-equipment capacity.
Evidence result:Eaton and Hitachi official announcements document planned expansion.
Ceiling effect:Bottleneck claim narrowed to current/vintage-specific conditions.
CTR-0041 · Efficiency response
Cooling, UPS and air-management choices can reduce infrastructure overhead.
Evidence result:DOE/NREL guidance and LBNL modeling identify technical mechanisms.
Ceiling effect:No named-site outcome.
Public-record gaps
NEG-0014
Question checked:Is public measured operating MW available for the four bounded C17 project records?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED. Operating states are disclosed, but common measured average/peak operating load is not.
Implication:No aggregate operating MW; unknown must not be recorded as zero.
NEG-0015
Question checked:Is sustained economic compute capacity C20 publicly established for any bounded Pass 02 project?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED. No record jointly establishes sustained utilization, customer use and economic output at project level.
Implication:C20 remains unassigned.
NEG-0049
Question checked:Do Abilene company disclosures establish C18–C20?
NO.
Implication:C17 only.
What could change this record
OIR-0019· Any bounded project receives a material cancellation, downsizing, land/permit decision, construction milestone, service agreement, energization, commissioning, phase redefinition, or portfolio-capacity reconciliation.Required update: Create dated state observation; preserve prior state; record supersession/overlap; update affected capacity fields without borrowing later-state language.
OIR-0020· Public evidence provides measured operating load, commissioned IT capacity, customer-use, utilization, revenue/economic incidence, or independent verification for a C17 project.Required update: Verify unit, period, site boundary and source function; upgrade only the supported state; preserve contrary evidence and C18–C20 distinctions.
OIR-0040· A newer authoritative component-specific lead-time dataset materially changes transformer, switchgear or related equipment evidence.Required update: Replace only the affected component/vintage; retain historic raw values.
OIR-0041· Supplier expansions enter production and disclose realized output or lead-time effects.Required update: Verify production start, output basis and market effect separately.
OIR-0042· Crusoe/GE Vernova turbine packages receive site allocation, delivery, installation, permits, fuel or operating evidence.Required update: Create site-specific states; do not aggregate expected GW into operating capacity.
Source register
Trace the public record
2 linked sources; rights and locators remain attached.
Source records
-
SRC-0066— Crusoe Announces Flagship Abilene Data Center is LiveCrusoe · 2025-09-30 · Tier A-minus
Locator: Construction began June 2024; first two buildings energized; first racks June 2025; early training and inference workloads running
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0067— Crusoe Expands AI Data Center Campus in Abilene to 1.2 GigawattsCrusoe · 2025-03-18 · Tier A-minus
Locator: 1.2 GW total campus design; initial two-building phase; six additional buildings under construction
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE