Interpretation guideGUIDE-03
No single institution can turn an announced campus into sustained economic compute.
Control is distributed across actors that issue different permissions, contracts, physical inputs and operating evidence. The exact sequence varies by jurisdiction, project structure and the C7–C10 service-model fork.
Executive summary
Read the conclusion before the archive.
- Control follows the transition: land, tariff, service, construction, energization and operation are governed by different actors.
- The selected service model changes the relevant regulator, utility relationship, document and capacity meaning.
- A company statement can establish its own disclosure but cannot substitute for public authority or measured operation.
01 · Core argument
The conversion chain is a sequence of distributed vetoes and permissions.
Institutional control is modular. An actor can control one transition while having no authority to establish the next.
Good analysis identifies the decision right, the controlling instrument and the exact scope of the resulting evidence.
02 · C7–C10 fork
The service model changes the control map.
Retail large-load service, transmission service, generator interconnection, co-location and behind-the-meter structures cannot borrow state or capacity from one another.
Signature model · C7–C10
One state vocabulary, five non-transferable service pathways
Each row requires its own authority, instrument, scope and evidence. A state or capacity measure cannot be borrowed from another row.
-
R Retail large-load service
Utility · state commission
- C7
Service request
- C8
Accepted utility review
- C9
Tariff or service class
- C10
Executed service obligation
-
T Transmission service
Transmission provider · RTO/ISO · FERC
- C7
Transmission request
- C8
Accepted system study
- C9
Transmission tariff path
- C10
Executed service obligation
-
G Generator interconnection
Interconnecting utility · RTO/ISO
- C7
Interconnection request
- C8
Accepted study stage
- C9
Interconnection tariff path
- C10
Executed agreement or obligation
-
C Co-location
Facility owner · utility · relevant regulator
- C7
Arrangement request
- C8
Technical or regulatory review
- C9
Applicable co-location path
- C10
Executed facility-specific obligation
-
B Behind the meter
Site owner · utility · local/state authority
- C7
On-site arrangement request
- C8
Engineering or compliance review
- C9
Ownership and service path
- C10
Executed on-site obligations
CLM-0053
03 · Actor map
Six institutional groups control different links.
The map assigns evidence functions, not blame or credit.
01
Developer and customer
Choose sites, disclose plans, contract for service, finance construction and decide deployment.
Cannot alone establish:public permission, delivered power or measured utilization.02
Local government and courts
Control land use, permits, incentives, environmental process and judicial review.
Cannot alone establish:grid service, energization or operation.03
Utility and state commission
Shape retail tariffs, contracts, deposits, cost assignment and service terms.
Cannot alone establish:construction completion or customer use.04
RTO/ISO and federal regulator
Control transmission procedures, tariff acceptance and regional planning mechanisms.
Cannot alone establish:participant-specific physical delivery.05
Equipment, construction and finance
Control transformers, generation, cooling, buildings, capital and schedule-critical inputs.
Cannot alone establish:commissioned service or economic output.06
Operator and customers
Commission infrastructure, install IT, run clusters and create customer-use and economic evidence.
Public limitation:downstream observations are often least standardized.04 · Permission stack
Ask three questions at every transition.
The same discipline applies whether the governing actor is public, private or mixed.
- 01
Who holds the decision right?
Name the institution or counterparty that can approve, condition, fund, deliver, commission or observe the transition.
- 02
Which instrument records the decision?
Use the order, tariff, agreement, permit, construction filing, operating statement or measured disclosure suited to that state.
- 03
What does the instrument not establish?
Publish the ceiling before using the event as evidence for a later link.
Decision boundary
Institutional attribution must remain transition-specific.
Permitted conclusion
Attribute a state or constraint to the actor and instrument that directly control or document that transition.
Prohibited stronger claim
Do not assign the entire chain, its timing or its outcome to one company, regulator, utility or court without evidence bridging the remaining links.
- Quantitative ceiling
- A regional rule or portfolio disclosure is not participant-specific capacity.
- Causal ceiling
- Control of one decision does not prove sole causation of the final outcome.
05 · Claim register
Institutional findings and their ceilings.
Every Claim ceiling and set of Linked sources remains inspectable.
CLM-0207 · interpretation
The case portfolio supports a modular permission stack controlled by different actors; no single regulator, utility, company or locality controls the full conversion chain.
- Claim ceiling
- Portfolio-level institutional finding; does not establish identical sequencing in every jurisdiction.
- Evidence
- Tier A · HIGH mechanism
- Locator
- Federal, RTO, state commission, court and project records
CLM-0053 · interpretation
No single U.S. “grid interconnection” state applies to all large loads: retail load service/interconnection, transmission service, generator interconnection, co-location, and behind-the-meter arrangements use different actors, instruments, studies, and jurisdictional pathways.
- Claim ceiling
- Pathway distinction only; no single source establishes a nationally uniform process.
- Evidence
- Tier A-minus · HIGH
- Locator
- FERC RM26-4 overview; FERC PJM order summary; MISO current-rules page; CAISO issue paper pp. 3-8; PJM pathway presentations
CLM-0020 · legal status
Ohio, Georgia, and Virginia have public regulatory records creating or approving large-load/data-center-specific rate or contract pathways, but their terms, procedural finality, and risk allocation differ and cannot be collapsed into one regime.
- Claim ceiling
- Existence and heterogeneity only; no conclusion that any regime fully protects ratepayers.
- Evidence
- Tier A · HIGH for existence; MEDIUM pending full tariff extraction
- Locator
- Ohio 24-508-EL-ATA and appeal 2025-1458; Georgia >100 MW summary/dockets; Virginia PUR-2025-00058/GS-5
CLM-0026 · implementation
Local land-use, water, and incentive records in Loudoun County, Prince William County, and Hillsboro demonstrate independently observable permission layers that cannot establish grid service or operation by themselves.
- Claim ceiling
- Source-universe/permission-layer finding only.
- Evidence
- Tier A · HIGH for source-layer distinction; LOW for unextracted project status
- Locator
- Named local-government pages and process records
CLM-0011 · interpretation
NERC’s March 2026 assessment identified gaps across interconnection, planning/resource adequacy, balancing/operations, ride-through/stability/power quality, security, resilience/event analysis, and load modeling.
- Claim ceiling
- NERC’s identified gap categories; not proof that every region lacks controls.
- Evidence
- Tier A · HIGH
- Locator
- Executive Summary p. vi
- Linked sources
SRC-0015
CLM-0186 · interpretation
Financing capacity is a distinct permission link: several companies disclose debt, equity, joint-venture, restricted-cash or asset-level financing dependencies that may accelerate or constrain infrastructure deployment.
- Claim ceiling
- Financing availability does not establish construction completion or operating capacity.
- Evidence
- Tier A · HIGH mechanism / company-specific outcomes vary
- Locator
- Financing and liquidity sections
CLM-0205 · interpretation
At least five rival theses win materially across the selected portfolio: forecast inflation/screening, policy and data uncertainty, partial private-risk allocation, local veto/process risk and demand-quality limits.
- Claim ceiling
- Rival wins are mechanism-specific and do not generalize to all U.S. projects.
- Evidence
- Tier A · HIGH for bounded portfolio findings
- Locator
- Selected case evidence and PASS_08_RIVAL_WIN_REGISTER.csv
Mechanisms that resist a single-controller explanation
CTR-0003 · Flexible-load response
Some computational loads may curtail, shift, or accept conditional service, reducing some system constraints.
Evidence result:FERC identifies flexible crypto-mining behavior as illustrative; SPP filed conditional HILL service; Virginia convened a flexibility record. Transferability to AI loads is unproven.
Ceiling effect:Possible mechanism only; not universal capability or solved reliability risk.
CTR-0004 · Private-risk allocation
Tariffs, collateral, minimum bills, contract terms, and exit provisions may shift material risk to large-load customers.
Evidence result:Ohio, Georgia, and Virginia records establish differentiated large-load rate/contract pathways, while consumer/intervenor records contest adequacy and legal status varies.
Ceiling effect:No claim that risk is fully shifted or ratepayers fully protected.
CTR-0005 · Local-benefit case
Data-center projects may provide tax base, infrastructure, and other public benefits that offset some costs.
Evidence result:Local incentive and development records are available in Hillsboro and Virginia, but audited net outcomes are not yet extracted.
Ceiling effect:Benefits and costs must be separately measured; no net-benefit conclusion.
CTR-0063 · Local veto and process risk
Prior local approval can be invalidated for process defects and remain uncertain during further appeal.
Evidence result:Virginia intermediate appellate opinion held three Digital Gateway rezonings void ab initio; appeal remains pending.
Ceiling effect:C21 legal state; not final cancellation.
CTR-0064 · Forecast inflation / private-risk allocation
Georgia’s framework and pipeline can both screen risk; disputed pipeline quantities may be revised as projects fail maturity tests.
Evidence result:The Commission adopted large-load protections; a docket participant identified removals and uncertainty. The latter remains party evidence.
Ceiling effect:Framework and uncertainty established; correct forecast not adjudicated here.
06 · Maintenance
Events that can reallocate or clarify control.
Changes in tariffs, orders, contracts, legal status or operating disclosure can move a transition to a different actor or instrument.
Events that could reallocate or clarify control
OIR-0006· NERC changes the guideline, closes the alert, advances Project 2026-02, changes registration, or FERC approves a standard.Required update: Version-control document; distinguish voluntary from mandatory; update exact obligations and effective dates.
OIR-0007· Ohio appeal resolves, or Ohio/Georgia/Virginia tariffs/contracts are modified, stayed, superseded, or implemented through new sheets/orders.Required update: Retrieve final holdings/effective sheets; record customer obligations, conditions, supersession, and legal finality.
OIR-0011· Selected localities issue new zoning, permit, water, incentive, appeal, or litigation records.Required update: Update application/permit/agreement state, conditions, appeal, capacity basis, and project crosswalk.
OIR-0046· A later periodic filing materially changes company capex, backlog, financing, power, project timing or utilization disclosures used in Pass 07.Required update: Inspect new 10-Q/10-K and record only material evidence deltas; do not refresh unchanged metrics each pass.
OIR-0056· New cross-case evidence materially changes a rival win or adaptation outcome.Required update: Update only affected case and preserve mechanism/outcome distinction.
Bibliography and exact locators
-
Federal Energy Regulatory Commission · 2026-01-13 · Tier A
Locator: Docket landing page; At a Glance; RM26-4-000; official page rechecked in Pass 09
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0083— Summaries — April 2026 Commission Meeting, Item E-1 ER26-1088-000Federal Energy Regulatory Commission · 2026-04-16 · Tier A
Locator: Item E-1, ER26-1088-000; order on compliance and directing further compliance
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0114— SCC Data Center Initiatives — Facts and FiguresVirginia State Corporation Commission · 2026-02 · Tier A-minus
Locator: pp. 1-2: 14-year obligation, 85% T&D minimum, up to 60% collateral, alternative cost-allocation filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0120— Digital Gateway rezoning appeals opinionCourt of Appeals of Virginia · 2026-03-31 · Tier A
Locator: Opinion pp. 4–5 and 52–53; records identified in Pass 05
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Federal Energy Regulatory Commission · 2026-06-05 · Tier A
Locator: 195 FERC ¶ 61,196; paras. 6–7, 104–105; ordering paras. A–B; effective July 1, 2026
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0010— FERC Directs PJM to Create New Rules for Co-Located Large LoadsFederal Energy Regulatory Commission · 2025-12-18 · Tier A-minus
Locator: Docket EL25-49-000; official order summary
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Midcontinent Independent System Operator · 2026-04-24 · Tier A-minus
Locator: Current-rules and issue-status sections; last modified 2026-04-24
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0087— Generator InterconnectionMidcontinent Independent System Operator · CURRENT PAGE AT CUTOFF · Tier A-minus
Locator: Process description and interconnection-agreement outcome
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
California Independent System Operator · 2026-01-20 / current page at cutoff · Tier A-minus
Locator: Roles in load interconnection, transmission planning, and generator interconnection
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0089— Large Loads Interconnection and Energization — Issue PaperCalifornia Independent System Operator · 2026-01-20 · Tier A-minus
Locator: PDF pp. 3-8 and 15-16
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0097— Large Load Additions Workshop — PresentationPJM Interconnection · 2025-05-09 · Tier A-minus
Locator: Pathway distinctions for network load, co-location and behind-the-meter generation
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0098— Large Load Additions Pre-CIFP Education — PJM PresentationPJM Interconnection · 2025-09-02 · Tier A-minus
Locator: Educational description of large-load additions and study interfaces
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0025— Electricity Rate Designs for Large Loads: Evolving Practices and OpportunitiesLawrence Berkeley National Laboratory · 2025-01-01 · Tier B
Locator: Rate-design taxonomy and examples
PUBLIC NATIONAL-LAB/TECHNICAL RECORD
-
SRC-0041— Data Centers — Ohio PUCO Resource PagePublic Utilities Commission of Ohio · 2025-07-09 · Tier A-minus
Locator: Case links and tariff resources
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0042— PUCO Orders AEP Ohio to Create Data Center-Specific TariffPublic Utilities Commission of Ohio · 2025-07-09 · Tier A-minus
Locator: Case 24-508-EL-ATA; official summary
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0043— Data Center Costs — Case 24-0508-EL-ATAOffice of the Ohio Consumers' Counsel · 2025-07-01 · Tier A-minus
Locator: Consumer-agency case summary and filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0044— Merit Brief, Supreme Court of Ohio Case 2025-1458Supreme Court of Ohio / appellant · 2026-02-02 · Tier A
Locator: Case 2025-1458; appellant merit brief; docket status
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0045— Georgia PSC Adopts Rules for Data Centers Over 100 MWGeorgia Public Service Commission · 2025-01-23 · Tier A-minus
Locator: p. 1; >100 MW threshold; contract/minimum-bill/cost provisions
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0046— Georgia Data Center Fact SheetGeorgia Public Service Commission · 2026-03-01 · Tier A-minus
Locator: p. 1 chronology and summary
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0047— Georgia PSC Docket 55378Georgia Public Service Commission · 2025-01-01 · Tier A
Locator: Docket index and filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0048— Georgia PSC Docket 44280Georgia Public Service Commission · 2025-01-01 · Tier A
Locator: Docket index; large-load contracts/filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0049— SCC Issues Order in Dominion Energy Virginia Biennial ReviewVirginia State Corporation Commission · 2025-11-25 · Tier A-minus
Locator: PUR-2025-00058; separate rate class
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0050— Virginia SCC Data Center InitiativesVirginia State Corporation Commission · 2026-02-01 · Tier A-minus
Locator: p. 2; GS-5 and initiatives
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0053— Data Center Standards & LocationsLoudoun County, Virginia · 2025-03-18 · Tier A
Locator: Adopted standards and location controls
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0054— Phase 2 Data Center Standards & LocationsLoudoun County, Virginia · 2026-01-01 · Tier A
Locator: Project milestones/status
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Prince William County, Virginia · 2025-01-01 · Tier A
Locator: Planning record and linked approvals
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0056— Data Centers in HillsboroCity of Hillsboro, Oregon · 2026-01-01 · Tier A-minus
Locator: City overview and links
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0057— Hillsboro Shares Data Center Water Use InformationCity of Hillsboro, Oregon · 2026-04-13 · Tier A-minus
Locator: Water-use disclosure and definitions
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0058— Hillsboro Enterprise Zone Agreements UpdateCity of Hillsboro, Oregon · 2026-05-08 · Tier A-minus
Locator: Agreement and moratorium update
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0059— Hillsboro Data Center Work Session UpdatesCity of Hillsboro, Oregon · 2026-06-02 · Tier A-minus
Locator: June 2026 work-session links
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
North American Electric Reliability Corporation · 2026-03-01 · Tier A
Locator: Executive Summary p. vi; gap categories
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0154— Quarterly Report on Form 10-Q for quarter ended February 28, 2026Oracle Corporation · 2026-03-10 · Tier A
Locator: Lines 1666–1670, 2948, 6529–6756; RPO, power obligations, capex and financing
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0155— CoreWeave, Inc. — Annual Report on Form 10-K for year ended December 31, 2025CoreWeave, Inc. · 2026-02-27 · Tier A
Locator: Lines 330–351; 3001–3041; active and contracted power, RPO, take-or-pay contracts, concentration and financing
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0157— Equinix, Inc. — Annual Report on Form 10-K for year ended December 31, 2025Equinix, Inc. · 2026-02-13 · Tier A
Locator: Lines 350–384; 1044–1045; 1553–1571; 1736–1756; 2191–2198; 5739; 6154–6167
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
American Electric Power Company, Inc. · 2026-04-29 · Tier A
Locator: Form 10-Q; large-load proposals and regulatory proceedings; pending proposals in Michigan, Oklahoma, Texas and Virginia
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0160— Dominion Energy, Inc. — Annual Report on Form 10-K for year ended December 31, 2025Dominion Energy, Inc. · 2026-02-20 · Tier A
Locator: PJM DOM Zone load-growth disclosure; Virginia regulated utility planning and capital-risk sections
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0006— Sunshine Notice — June 2026 Commission MeetingFederal Energy Regulatory Commission · 2026-06-11 · Tier A
Locator: Agenda Item E-1; RM26-4-000
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0038— ERCOT Large Load Update — House State Affairs HearingElectric Reliability Council of Texas · 2026-04-09 · Tier A-minus
Locator: Aggregate request total and composition slides
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Georgia PSC public docket participant filing · 2025-12-16 · Tier A-minus
Locator: PDF pp. 6–10 and 17; discusses 14,345 MW removal, pipeline screening, contract uncertainty and flexibility assumptions
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0066— Crusoe Announces Flagship Abilene Data Center is LiveCrusoe · 2025-09-30 · Tier A-minus
Locator: Construction began June 2024; first two buildings energized; first racks June 2025; early training and inference workloads running
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0012— 2025 State of the Markets ReportFederal Energy Regulatory Commission, Office of Enforcement · 2026-03-26 · Tier A
Locator: PDF pp. 9–10 (report pp. 7–8), Figure 5 and note 14; other market-review figures as separately cited
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0036— SPP Conditional High Impact Large Load Service FilingSouthwest Power Pool · 2026-02-10 · Tier A
Locator: ER26-1323-000; proposed conditional service terms
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0051— Technical Conference on Data Center Load FlexibilityVirginia State Corporation Commission · 2025-10-24 · Tier A-minus
Locator: Conference scope/date
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0121— Virginia appeals list associated with Digital Gateway recordsVirginia appellate courts · 2026-06-02 · Tier A
Locator: Appeals list p. 1
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0100— Order Approving Georgia Power Rules and Regulations Changes for Large CustomersGeorgia Public Service Commission · 2025-01-28 · Tier A
Locator: Docket 44280, Document 221165, pp. 1-3; ordering paragraphs on implementation, contract filing, compliance tariff, continuing jurisdiction
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0169— 147th Annual Report — Georgia Public Service CommissionGeorgia Public Service Commission · 2026-05-12 · Tier A-minus
Locator: Data-center/large-load rule discussion; >100 MW customers; minimum billing, longer terms and pre-execution contract filing; 2025 activity summary
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE