Interpretation guideGUIDE-01
An announcement is the first record, not the last test.
A plan becomes economically usable compute only after distinct land, approval, service, construction, energization, commissioning, IT, customer-use and economic-output questions are answered. The sequence is modular, can overlap and can reverse.
Executive summary
Read the conclusion before the archive.
- Each transition requires evidence suited to that transition; an upstream record cannot substitute for a downstream observation.
- The service-model fork at C7–C10 changes the relevant actors, documents and capacity meaning.
- C20 requires sustained evidence connecting operation, customer use and economic output at a bounded scope.
01 · Core argument
The evidence changes function as the project changes state.
A public announcement establishes intent. It does not establish site control, lawful permission, grid service, physical delivery, operating compute or economic use.
Every later label must be supported independently and scoped to the named project, phase, cohort or disclosure.
02 · Conversion chain
Five evidence regimes, twenty-one controlled transitions.
The path can branch, pause, contract, reverse or terminate. The state model records evidence, not inevitability.
- C0–C6
Intent, site and permission
Announcements, site control and local approvals establish progressively firmer intent and lawful pathway. They do not establish service or construction.
- C7–C10
Power pathway and service-model fork
Requests, studies, tariff pathways and executed obligations have different legal and technical meanings. Contractual permission remains distinct from delivered electricity.
- C11–C14
Physical delivery
Funded upgrades, construction, equipment delivery and energization require separate records. A campus total may remain announced while only a bounded phase advances.
- C15–C17
Compute operation
Commissioning, IT installation and cluster operation narrow the gap, but public operating MW and comparable utilization can remain unknown.
- C18–C20
Observed economic use
Contracted use, measured utilization or revenue and sustained economic capacity require downstream observations that are least standardized publicly.
Signature model · C7–C10
One state vocabulary, five non-transferable service pathways
Each row requires its own authority, instrument, scope and evidence. A state or capacity measure cannot be borrowed from another row.
-
R Retail large-load service
Utility · state commission
- C7
Service request
- C8
Accepted utility review
- C9
Tariff or service class
- C10
Executed service obligation
-
T Transmission service
Transmission provider · RTO/ISO · FERC
- C7
Transmission request
- C8
Accepted system study
- C9
Transmission tariff path
- C10
Executed service obligation
-
G Generator interconnection
Interconnecting utility · RTO/ISO
- C7
Interconnection request
- C8
Accepted study stage
- C9
Interconnection tariff path
- C10
Executed agreement or obligation
-
C Co-location
Facility owner · utility · relevant regulator
- C7
Arrangement request
- C8
Technical or regulatory review
- C9
Applicable co-location path
- C10
Executed facility-specific obligation
-
B Behind the meter
Site owner · utility · local/state authority
- C7
On-site arrangement request
- C8
Engineering or compliance review
- C9
Ownership and service path
- C10
Executed on-site obligations
Signature model · C17–C20
The evidence boundary becomes less observable after operation
The gradient represents public-record visibility, not the existence or absence of private activity.
- C17Threshold observation
Operating infrastructure
A bounded operating statement or equivalent observation.
Boundary: Does not establish customer use, utilization or project economics.
- C18Commercial bridge
Contracted use
A scoped arrangement linking operating capacity to customer use.
Boundary: Contract scope, customer identity or capacity denominator may remain private.
- C19Measured downstream use
Utilization or revenue
A comparable measure with denominator, period and project scope.
Boundary: Portfolio or company-wide metrics may not isolate the named project.
- C20Durable operating-economic bridge
Sustained economic capacity
Evidence connecting sustained operation, use and economic output.
Boundary: Public project-level evidence is often absent or non-comparable.
Unknown is not zero. Missing public C18–C20 evidence is recorded as a scoped gap, not as proof of full utilization, failure or stranded capacity.
Decision boundary
The strongest conclusion must stop at the last supported transition.
Permitted conclusion
A record may be described at the highest state established for its bounded scope, with the controlling source, unit basis and cutoff retained.
Prohibited stronger claim
Do not translate an announcement, request, forecast, tariff, contract or portfolio disclosure into delivered, operating or economically utilized capacity without bridge evidence.
- Quantitative ceiling
- No cross-state or cross-register total.
- Causal ceiling
- No delay, success or failure attribution without a documented mechanism.
04 · Failure modes
Why the chain can stop, change or reverse.
Rival explanations become material when they alter the meaning of a prior event or block the bridge to the next state.
Permission without service
Land and local approvals can be real while the selected service pathway remains unresolved.
Contract without delivery
An executed obligation can define terms without establishing energization, average load or installed compute.
Construction without full scope
A visible build can support a phase claim while the announced campus total remains unverified.
Operation without economic observation
An operating disclosure does not automatically establish contracted use, utilization, revenue or C20.
Rival evidence that narrows the conversion claim
CTR-0059 · Contract architecture is not physical delivery
A revised front-of-the-meter PPA may adapt the arrangement without proving delivered or consumed load.
Evidence result:Talen discloses up to 1,920 MW and a transition date, but no campus energization, average load or utilization.
Ceiling effect:C10 maximum.
CTR-0061 · Demand-quality problem / non-power bottlenecks
Construction or company-asserted operation does not prove measured utilization or sustained economic capacity.
Evidence result:Abilene and Mount Pleasant records stop at C17 assertion and C12 construction respectively, without C18–C20 evidence.
Ceiling effect:C20 prohibited.
CTR-0065 · Flexible-load response
Conditional non-firm service can create an earlier pathway, but it may expose load to curtailment and does not establish participation or outcome.
Evidence result:FERC accepted voluntary CHILLS as conditional/as-available service subject to compliance.
Ceiling effect:C9 pathway only.
05 · Claim register
What the archive permits this guide to say.
Each claim retains its ceiling, evidence class, exact locator and Linked sources.
CLM-0005 · interpretation
Announced, requested, approved, contracted, deliverable, energized, installed, utilized, and economically productive capacity are non-equivalent states and units.
- Claim ceiling
- No conversion without an explicit method and evidence.
- Evidence
- CONTROLLING/BOUNDING INPUT · HIGH
- Locator
- Operating Prompt §7; Seed Charter §6
- Linked sources
SRC-0001internal recordSRC-0002internal record
CLM-0015 · interpretation
The ER24-2172 order demonstrates that an interconnection-service-agreement amendment and a stated behind-meter load allowance are contractual/regulatory states, not proof of energization, commissioned IT capacity, or economic use.
- Claim ceiling
- Maximum state ceiling C10 absent later public evidence.
- Evidence
- Tier A + CONTROLLING INPUT · HIGH
- Locator
- SRC-0008 pp. 5–7; Operating Prompt §7
- Linked sources
SRC-0008SRC-0001internal record
CLM-0204 · implementation
Microsoft Mount Pleasant provides C12 construction evidence but no public C14–C20 bridge; phased construction is a supply-response mechanism, not operating-capacity proof.
- Claim ceiling
- No energized MW, commissioning, installed IT, utilization or C20.
- Evidence
- Tier A-minus · MEDIUM-HIGH C12
- Locator
- March/April 2026 construction updates and municipal project page
CLM-0206 · interpretation
No selected case reaches public C20 sustained economic compute capacity at cutoff.
- Claim ceiling
- Absence of public C20 proof is not proof that no private economic capacity exists.
- Evidence
- Tier A · HIGH
- Locator
- Case reachability profiles and named project disclosures
CLM-0208 · outcome
Conditional service, phased construction, tariff security and contractual restructuring are documented adaptations, but their observed effects on schedule, utilization, rates and economic output remain mostly unproven.
- Claim ceiling
- Do not treat adaptation availability as proof that the underlying bottleneck is solved.
- Evidence
- Tier A · HIGH mechanisms / LOW outcomes
- Locator
- CHILLS order; Mount Pleasant update; GS-5 fact sheet; Talen 10-Q
Public-record gaps
NEG-0006
Question checked:Is there a standardized national public record for commissioning and utilization?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED.
Implication:Require project-specific C15–C20 evidence.
NEG-0014
Question checked:Is public measured operating MW available for the four bounded C17 project records?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED. Operating states are disclosed, but common measured average/peak operating load is not.
Implication:No aggregate operating MW; unknown must not be recorded as zero.
NF-0059
Question checked:Is named-site C20 sustained economic compute capacity established?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED
Implication:C20 remains prohibited.
06 · Maintenance
Evidence that can change this guide.
The model is stable; the status of individual records changes only when a controlling event or observation is documented.
Evidence that could change this guide
OIR-0012· New public evidence changes equipment lead-time, delivery, construction, energization, or commissioning status.Required update: Record source vintage, item, order/delivery/install/test state, and non-comparability.
OIR-0019· Any bounded project receives a material cancellation, downsizing, land/permit decision, construction milestone, service agreement, energization, commissioning, phase redefinition, or portfolio-capacity reconciliation.Required update: Create dated state observation; preserve prior state; record supersession/overlap; update affected capacity fields without borrowing later-state language.
OIR-0020· Public evidence provides measured operating load, commissioned IT capacity, customer-use, utilization, revenue/economic incidence, or independent verification for a C17 project.Required update: Verify unit, period, site boundary and source function; upgrade only the supported state; preserve contrary evidence and C18–C20 distinctions.
OIR-0049· Comparable public utilization, average-load or C20 evidence becomes available for CoreWeave, Equinix xScale or a named operating AI cluster.Required update: Normalize meter boundary, time period, denominator, AI share and economic measure before state upgrade.
OIR-0056· New cross-case evidence materially changes a rival win or adaptation outcome.Required update: Update only affected case and preserve mechanism/outcome distinction.
Bibliography and exact locators
-
SRC-0001— AI Compute Infrastructure — autonomous research operating promptOperator-supplied controlling input · 2026-06-18 · CONTROLLING INPUT
Locator: Full file; sections 0–14
OPERATOR-SUPPLIED PROGRAM INPUT
-
SRC-0002— AI Compute Infrastructure — research seed charterOperator-supplied bounded brief · 2026-06-18 · BOUNDING INPUT
Locator: Full file; sections 1–14
OPERATOR-SUPPLIED PROGRAM INPUT
-
Federal Energy Regulatory Commission · 2024-11-01 · Tier A
Locator: 189 FERC ¶ 61,078; pp. 5–7; paras. 6–11; ordering paragraphs
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0068— Mount Pleasant datacenter project updateMicrosoft · 2026-04-09 · Tier A-minus
Locator: March 2026 update: Phase 1 nearing completion; Phase 2 construction; Phase 3 earthwork
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0129— Stack PDX air permit enforcement final orderOregon Department of Environmental Quality · 2025-01-09 · Tier A
Locator: Final order pp. 1–2
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0161— Talen Energy Corporation — Quarterly Report on Form 10-Q for quarter ended March 31, 2026Talen Energy Corporation · 2026-05-05 · Tier A
Locator: Glossary lines 2053–2056; revised AWS PPA up to 1,920 MW through 2042; transition in April 2026
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0066— Crusoe Announces Flagship Abilene Data Center is LiveCrusoe · 2025-09-30 · Tier A-minus
Locator: Construction began June 2024; first two buildings energized; first racks June 2025; early training and inference workloads running
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0120— Digital Gateway rezoning appeals opinionCourt of Appeals of Virginia · 2026-03-31 · Tier A
Locator: Opinion pp. 4–5 and 52–53; records identified in Pass 05
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Federal Energy Regulatory Commission · 2026-06-05 · Tier A
Locator: 195 FERC ¶ 61,196; paras. 6–7, 104–105; ordering paras. A–B; effective July 1, 2026
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0114— SCC Data Center Initiatives — Facts and FiguresVirginia State Corporation Commission · 2026-02 · Tier A-minus
Locator: pp. 1-2: 14-year obligation, 85% T&D minimum, up to 60% collateral, alternative cost-allocation filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0067— Crusoe Expands AI Data Center Campus in Abilene to 1.2 GigawattsCrusoe · 2025-03-18 · Tier A-minus
Locator: 1.2 GW total campus design; initial two-building phase; six additional buildings under construction
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0023— 2024 United States Data Center Energy Usage ReportLawrence Berkeley National Laboratory / U.S. Department of Energy · 2024-12-19 · Tier A
Locator: Executive Summary pp. 5–7; Figure 5.5 pp. 52–53; methods and limitations
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0028— Large Load Literature Review Data SourcesLawrence Berkeley National Laboratory · 2026-03-01 · Tier B
Locator: Source inventory and definitions
PUBLIC NATIONAL-LAB/TECHNICAL RECORD
-
SRC-0071— Meta’s Kansas City Data Center is now operationalMeta · 2025-08-01 · Tier A-minus
Locator: Company statement that facility is operational and serving traffic
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
xAI · UNSTATED — CURRENT PAGE AT RETRIEVAL · Tier A-minus
Locator: Company statement: 200,000 NVIDIA H100 GPUs in a single interconnected cluster
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0076— Google announces new investment in Jackson County, Alabama data centerGoogle · 2026-06-15 · Tier A-minus
Locator: Existing campus operating since 2019; $1.5 billion expansion announced for 2026–2027
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0155— CoreWeave, Inc. — Annual Report on Form 10-K for year ended December 31, 2025CoreWeave, Inc. · 2026-02-27 · Tier A
Locator: Lines 330–351; 3001–3041; active and contracted power, RPO, take-or-pay contracts, concentration and financing
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE