Interpretation guideGUIDE-02
The same number can describe a request, a scenario, a contract or a physical load.
The Evidence Ledger keeps each figure attached to its register, state, unit basis, geography, vintage and caveat. A cross-record total is prohibited when any of those dimensions differ.
Executive summary
Read the conclusion before the archive.
- A shared MW label does not create a shared denominator.
- Forecast, request, contract, energized load, MW-IT, average MW and annual energy answer different questions.
- A conversion is allowed only when explicit bridge data and assumptions are published.
01 · Core argument
A number is not portable across evidence regimes.
Every quantity remains attached to what it measures, when it was observed, which geography it covers and which state it describes.
The absence of those dimensions makes an impressive total less informative, not more.
02 · Four-register discipline
Load, Supply, Money and AI-share are separate ledgers.
They can be read together as context. They cannot be collapsed into a single AI-compute capacity figure.
Four-register discipline
Every figure stays inside its evidentiary register.
Movement between registers requires an explicit, source-stated bridge. Missing bridge data remains unknown rather than being imputed.
-
R01
Load
Requests, forecasts, design power, energized load, average MW and energy remain distinct.
CLM-0005CLM-0033 -
R02
Supply
Service model, deliverability, generation and physical inputs stay attached to their own pathway.
CLM-0053 -
R03
Money
Capex, backlog, RPO, contracted power, revenue and utilization are not bridge-equivalent.
CLM-0180 -
R04
AI-share
Total data-center measures are not AI-only unless the source supplies the cut.
CLM-0029
AI-share boundary
Broader infrastructure does not become AI-only by implication
The source must define which part of the broader quantity is attributable to AI.
03 · Quantity types
Six familiar labels answer six different questions.
The comparison below is semantic, not additive.
- Requested MW
- What a customer asked a utility or grid process to study. It is not approval or delivery.
- Forecast MW or GW
- What a planning model includes under defined assumptions and screening rules. It is not a queue total.
- Contracted MW
- What an agreement or company disclosure describes. It is not energized or average load.
- Energized MW
- What electrical infrastructure has reached a live state. It does not by itself establish installed or utilized compute.
- MW-IT, average MW and annual MWh/TWh
- Equipment load, time-averaged power and annual energy are different physical measures. Conversion requires explicit assumptions.
- Economic or utilization measures
- Revenue backlog, active power, cabinet utilization and customer use have different definitions and cannot be translated without bridge data.
04 · Bridge test
A conversion requires a denominator, period and mechanism.
Without all three, the original quantity may be reported but not translated.
Same object and scope?
Portfolio, region, campus, phase and building totals cannot be substituted for one another.
Same state and time basis?
Requested, contracted, peak, average and annual values describe different observations.
Published conversion rule?
Efficiency, load factor, PUE, duration and AI-share assumptions must be explicit.
Two-sided gap
The conversion gap can widen from either side.
Upstream contraction: screening, service-model limits, policy uncertainty and local process can reduce or delay the quantity that reaches operation.
CLM-0205CTR-0001
Demand-side contraction: efficiency, forecast revision and demand quality can reduce the load or economic use associated with an upstream figure.
CTR-0002CTR-0007
Decision boundary
No synthetic total
Permitted conclusion
Display each figure with its original label, state, unit basis, geography, vintage and caveat.
Prohibited stronger claim
Do not add, rank or convert heterogeneous figures into a market total or realization percentage.
- Quantitative ceiling
- Not summable in this edition.
- Causal ceiling
- No quantity alone establishes the mechanism that produced it.
05 · Claim register
Evidence boundaries behind the unit rules.
Each Claim ceiling and set of Linked sources remains visible for audit.
CLM-0005 · interpretation
Announced, requested, approved, contracted, deliverable, energized, installed, utilized, and economically productive capacity are non-equivalent states and units.
- Claim ceiling
- No conversion without an explicit method and evidence.
- Evidence
- CONTROLLING/BOUNDING INPUT · HIGH
- Locator
- Operating Prompt §7; Seed Charter §6
- Linked sources
SRC-0001internal recordSRC-0002internal record
CLM-0029 · forecast
LBNL estimates U.S. data centers used about 176 TWh in 2023, approximately 4.4% of U.S. electricity; this is a modeled total-data-center baseline, not AI-only demand or operating site capacity.
- Claim ceiling
- National total-data-center annual energy estimate only; no AI-only or project-state inference.
- Evidence
- Tier A · HIGH for report values; MEDIUM for national estimate precision
- Locator
- Executive Summary pp. 5–7; historical series and Figure 5.5
- Linked sources
SRC-0023
CLM-0033 · interpretation
TWh/year, equivalent average GW, source-defined facility capacity, system peak GW, requested load, design capacity, MW-IT, GPU count, and announced capex are non-interchangeable metrics and are held in separate comparable groups.
- Claim ceiling
- Normalization rule; no conversion beyond explicit formula and assumptions.
- Evidence
- Tier A + CONTROLLING INPUT · HIGH
- Locator
- Operating Prompt §§7–8; Seed Charter §§3,6; quantitative source locators in Pass 02 ledgers
CLM-0016 · forecast
PJM’s 2026 load forecast process screens large-load adjustment requests rather than automatically including the full requested amount.
- Claim ceiling
- Forecast-inclusion method, not validation of each included project.
- Evidence
- Tier A · HIGH
- Locator
- SRC-0029 methodology; SRC-0030 criteria; SRC-0031 slides 30–31
CLM-0019 · interpretation
ERCOT’s April 2026 aggregate of roughly 410 GW seeking interconnection is a request-pipeline measure, not approved, deliverable, energized, or forecast peak load.
- Claim ceiling
- Request-pipeline snapshot only; no project count or capacity realization rate.
- Evidence
- Tier A · HIGH
- Locator
- SRC-0038 aggregate request slides; process page
CLM-0098 · technical state
A reported contract or committed MW quantity is a contractual/company-disclosure state and cannot be counted as deliverable power, energized load, average consumption or operating AI capacity.
- Claim ceiling
- No capacity-state upgrade without project-specific evidence.
- Evidence
- Tier A-minus · HIGH
- Locator
- Company aggregate contract disclosures
CLM-0180 · interpretation
RPO, revenue backlog, equipment backlog, active power, contracted power, cabinet utilization and development capacity are non-equivalent measures.
- Claim ceiling
- No cross-metric aggregation or conversion to economic compute without disclosed bridge data.
- Evidence
- Tier A · HIGH
- Locator
- Referenced filing definitions
CLM-0205 · interpretation
At least five rival theses win materially across the selected portfolio: forecast inflation/screening, policy and data uncertainty, partial private-risk allocation, local veto/process risk and demand-quality limits.
- Claim ceiling
- Rival wins are mechanism-specific and do not generalize to all U.S. projects.
- Evidence
- Tier A · HIGH for bounded portfolio findings
- Locator
- Selected case evidence and PASS_08_RIVAL_WIN_REGISTER.csv
Rival evidence that narrows pipeline, demand and contract figures
CTR-0001 · Forecast inflation
Requested and announced pipelines can materially exceed screened forecasts or realized load.
Evidence result:PJM differentiates utility demand asks from preliminary/final included adjustments; FERC reported a 15% lower 2032 AEP-zone forecast versus the prior vintage after large-load adjustments.
Ceiling effect:No pipeline-to-realization conversion; preserve vintage and screening.
CTR-0002 · Efficiency response
Hardware, software, workload, and facility efficiency can reduce energy per useful compute and alter forecast demand.
Evidence result:The LBNL national report explicitly models efficiency, utilization, shipments, and cooling assumptions and records historical efficiency effects.
Ceiling effect:Forecasts require scenario ranges; no fixed power-per-compute assumption.
CTR-0007 · Demand-quality problem
Contracted or installed capacity may not yield high utilization, customer use, revenue, or durable economic output.
Evidence result:NOVEC testimony shows a large difference between served and contracted aggregate load; the program’s C18–C20 states require later operating/economic evidence.
Ceiling effect:No contracted-to-utilized/economic conversion.
CTR-0008 · Policy and data uncertainty
Evolving rules, changing forecast vintages, and inconsistent definitions may be a principal planning and evidentiary cost.
Evidence result:FERC, NERC, PJM, ERCOT, and state records are contemporaneously changing and use different units/states.
Ceiling effect:Every current claim requires cutoff and reopen trigger.
CTR-0030 · Forecast inflation / demand-quality
Contract and commitment aggregates do not establish project realization.
Evidence result:Georgia company disclosures lack a public project-level deliverability/energization crosswalk.
Ceiling effect:No pipeline or operating-capacity addition.
Public-record gaps
NEG-0013
Question checked:Can FERC’s reported >50 GW in-service data-center capacity be reproduced project by project from the public report?
SOURCE GAP CONFIRMED IN PASS 09. The FERC report identifies a Yes Energy Load Center Project Database source, while public Yes Energy pages describe a proprietary/commercial dataset but do not publish project-level inclusion, status-transition, duplicate-control or C14–C20 reconciliation rules sufficient for reproduction.
Implication:Use only as a source-defined external benchmark; do not add to the project ledger or treat “in service” as a program C-state.
NEG-0014
Question checked:Is public measured operating MW available for the four bounded C17 project records?
UNKNOWN — PUBLIC EVIDENCE NOT LOCATED. Operating states are disclosed, but common measured average/peak operating load is not.
Implication:No aggregate operating MW; unknown must not be recorded as zero.
NEG-0022
Question checked:Can ERCOT aggregate large-load interest be reconciled to project-level approved, deliverable and energized MW?
SOURCE GAP. Aggregate interest/process evidence does not provide a complete public project-level C7–C17 crosswalk.
Implication:No project realization ratio or operating total from aggregate request figures.
06 · Maintenance
Evidence that can change a quantity or its basis.
Revisions are recorded when the source publishes a changed value, denominator, period, state or conversion method.
Evidence that could change a quantity or its basis
OIR-0005· ERCOT releases a newer large-load request, screening, forecast, withdrawal, or interconnection-status dataset.Required update: Preserve prior snapshot; add new vintage, state definitions, attrition/duplication changes, and affected aggregates.
OIR-0008· New official demand forecast, project pipeline, operational-data accuracy report, or material project cancellation/energization is published.Required update: Add vintage rather than overwrite; reconcile project IDs; update state and double-counting register.
OIR-0017· A new official national or regional demand forecast, AEO/LBNL update, or method revision changes scope, horizon, scenario range, or unit bridge.Required update: Add new vintage without deleting prior; reconcile scope, method, denominator and supersession; rerun normalization.
OIR-0020· Public evidence provides measured operating load, commissioned IT capacity, customer-use, utilization, revenue/economic incidence, or independent verification for a C17 project.Required update: Verify unit, period, site boundary and source function; upgrade only the supported state; preserve contrary evidence and C18–C20 distinctions.
OIR-0030· Project-level official records resolve Georgia aggregate contracts/commitments into request, contract, construction, energization or operating states.Required update: Create project-specific state observations; prevent double counting and preserve units.
Bibliography and exact locators
-
SRC-0001— AI Compute Infrastructure — autonomous research operating promptOperator-supplied controlling input · 2026-06-18 · CONTROLLING INPUT
Locator: Full file; sections 0–14
OPERATOR-SUPPLIED PROGRAM INPUT
-
SRC-0002— AI Compute Infrastructure — research seed charterOperator-supplied bounded brief · 2026-06-18 · BOUNDING INPUT
Locator: Full file; sections 1–14
OPERATOR-SUPPLIED PROGRAM INPUT
-
SRC-0023— 2024 United States Data Center Energy Usage ReportLawrence Berkeley National Laboratory / U.S. Department of Energy · 2024-12-19 · Tier A
Locator: Executive Summary pp. 5–7; Figure 5.5 pp. 52–53; methods and limitations
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0012— 2025 State of the Markets ReportFederal Energy Regulatory Commission, Office of Enforcement · 2026-03-26 · Tier A
Locator: PDF pp. 9–10 (report pp. 7–8), Figure 5 and note 14; other market-review figures as separately cited
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0018— 2025 Long-Term Reliability AssessmentNorth American Electric Reliability Corporation · 2026-01-23 · Tier A
Locator: PDF p. 16 for PJM 210/56 GW; PDF p. 131 for ERCOT 6,700/23,000/25,000 MW and realization calibration
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0029— 2026 PJM Load Forecast ReportPJM Interconnection · 2026-01-14 · Tier A
Locator: Executive summary; large-load adjustment methodology; zone tables
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0030— Load Adjustment Request ImplementationPJM Interconnection · 2025-07-01 · Tier A-minus
Locator: Implementation criteria and process
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0031— Load Adjustment Requests Summary for 2026 Load ForecastPJM Interconnection · 2025-11-24 · Tier A-minus
Locator: Slides 30–31; ask versus preliminary included
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0037— Large Load IntegrationElectric Reliability Council of Texas · 2026-01-01 · Tier A-minus
Locator: Current forms and process links
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0038— ERCOT Large Load Update — House State Affairs HearingElectric Reliability Council of Texas · 2026-04-09 · Tier A-minus
Locator: Aggregate request total and composition slides
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0039— 2025 ERCOT Annual ReportElectric Reliability Council of Texas · 2026-03-19 · Tier A
Locator: Large-load and planning sections
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0101— Georgia Power highlights first contracts under new rules and regulationsGeorgia Power · 2025-09-30 · Tier A-minus
Locator: Lines 251-264; nearly 2 GW of new contracts filed; additional negotiations and forecast assertions
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0116— Georgia Power plans additional generation and reports large-load commitmentsGeorgia Power · 2026-04-23 · Tier A-minus
Locator: 32 large-load customers committed to approximately 15,600 MW; 21 projects under construction; resource requests remain subject to PSC process
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0152— Alphabet Inc. — Quarterly Report on Form 10-Q for quarter ended March 31, 2026Alphabet Inc. · 2026-04-23 · Tier A
Locator: Lines 590; 1968–1972; 2206–2217; capital expenditures, Cloud RPO, asset placement in service
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0154— Quarterly Report on Form 10-Q for quarter ended February 28, 2026Oracle Corporation · 2026-03-10 · Tier A
Locator: Lines 1666–1670, 2948, 6529–6756; RPO, power obligations, capex and financing
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0155— CoreWeave, Inc. — Annual Report on Form 10-K for year ended December 31, 2025CoreWeave, Inc. · 2026-02-27 · Tier A
Locator: Lines 330–351; 3001–3041; active and contracted power, RPO, take-or-pay contracts, concentration and financing
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0156— CoreWeave Reports Strong First Quarter 2026 ResultsCoreWeave, Inc. / SEC Exhibit 99.1 · 2026-05-07 · Tier A-minus
Locator: First-quarter 2026 financial highlights; revenue backlog $99.4 billion at 2026-03-31
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0157— Equinix, Inc. — Annual Report on Form 10-K for year ended December 31, 2025Equinix, Inc. · 2026-02-13 · Tier A
Locator: Lines 350–384; 1044–1045; 1553–1571; 1736–1756; 2191–2198; 5739; 6154–6167
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0162— Eaton Corporation plc — Quarterly Report on Form 10-Q for quarter ended March 31, 2026Eaton Corporation plc · 2026-05-05 · Tier A
Locator: Lines 492–493, 1128–1163; backlog, data-center demand, margins; acquisition notes lines 327–396
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0163— Vertiv Holdings Co — Annual Report on Form 10-K for year ended December 31, 2025Vertiv Holdings Co · 2026-02-18 · Tier A
Locator: Lines 378–389 and 637–639; combined backlog, delivery expectation, cancellation/rescheduling risk
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0164— GE Vernova Reports First Quarter 2026 Financial ResultsGE Vernova Inc. / SEC Exhibit 99.1 · 2026-04-22 · Tier A-minus
Locator: Lines 40–53; $2.4 billion Electrification equipment orders supporting data centers; total orders and revenue
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0006— Sunshine Notice — June 2026 Commission MeetingFederal Energy Regulatory Commission · 2026-06-11 · Tier A
Locator: Agenda Item E-1; RM26-4-000
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0114— SCC Data Center Initiatives — Facts and FiguresVirginia State Corporation Commission · 2026-02 · Tier A-minus
Locator: pp. 1-2: 14-year obligation, 85% T&D minimum, up to 60% collateral, alternative cost-allocation filings
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0120— Digital Gateway rezoning appeals opinionCourt of Appeals of Virginia · 2026-03-31 · Tier A
Locator: Opinion pp. 4–5 and 52–53; records identified in Pass 05
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Georgia PSC public docket participant filing · 2025-12-16 · Tier A-minus
Locator: PDF pp. 6–10 and 17; discusses 14,345 MW removal, pipeline screening, contract uncertainty and flexibility assumptions
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Federal Energy Regulatory Commission · 2026-06-05 · Tier A
Locator: 195 FERC ¶ 61,196; paras. 6–7, 104–105; ordering paras. A–B; effective July 1, 2026
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0066— Crusoe Announces Flagship Abilene Data Center is LiveCrusoe · 2025-09-30 · Tier A-minus
Locator: Construction began June 2024; first two buildings energized; first racks June 2025; early training and inference workloads running
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0032— Load Forecast Accuracy Report — May 2026PJM Interconnection · 2026-05-29 · Tier A
Locator: Overview p. 3; operational-data comparisons
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0027— Best Practice Guide for Data Center DesignU.S. Department of Energy · 2024-07-01 · Tier A-minus
Locator: Full guide
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0052— NOVEC Evidence for Virginia Load Growth Technical ConferenceVirginia SCC docket / Northern Virginia Electric Cooperative · 2024-12-16 · Tier A-minus
Locator: Testimony: 58 buildings; 1,408 MW served; 3,513 MW contracted
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
Federal Energy Regulatory Commission · 2026-01-13 · Tier A
Locator: Docket landing page; At a Glance; RM26-4-000; official page rechecked in Pass 09
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
North American Electric Reliability Corporation · 2026-03-01 · Tier A
Locator: Executive Summary p. vi; gap categories
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0040— Long-Term Load Forecast Update 2025–2031 and Methodology ChangesElectric Reliability Council of Texas · 2025-04-07 · Tier A-minus
Locator: Forecast methodology and adjustments
PUBLIC OFFICIAL RECORD — CITE/SUMMARIZE
-
SRC-0071— Meta’s Kansas City Data Center is now operationalMeta · 2025-08-01 · Tier A-minus
Locator: Company statement that facility is operational and serving traffic
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
xAI · UNSTATED — CURRENT PAGE AT RETRIEVAL · Tier A-minus
Locator: Company statement: 200,000 NVIDIA H100 GPUs in a single interconnected cluster
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE
-
SRC-0076— Google announces new investment in Jackson County, Alabama data centerGoogle · 2026-06-15 · Tier A-minus
Locator: Existing campus operating since 2019; $1.5 billion expansion announced for 2026–2027
PUBLIC COMPANY/SEC RECORD — CITE/SUMMARIZE